Azteca Hot Commissioning Complete

Summary by AI BETAClose X

Cadence reports DEV completed hot commissioning of the Azteca plant in 30 days of a 45-day consent window, processing ~6,200 wet tonnes (~5,700 dry) of feed and producing ~2,800 wet tonnes (~2,600 dry) of concentrate (mass recovery ~45%), running at ~40 wet t/h (roughly one-third of ~110 t/h capacity); assay results are pending and optimisation testwork results are expected in 4–6 weeks; the Operating Licence remains pending and commercial operations/shipments are subject to its grant; the production target of ~380,000 tpa of ~65% Fe concentrate is unchanged; Cadence has invested ~US$16.1m and holds a 36.2% equity interest in the operator.