Azteca Execution Update

AI SummaryClose X

Cadence Minerals Plc has provided an update on the Azteca plant refurbishment at the Amapá Iron Ore Project, reporting that weighted physical progress has reached 48%, exceeding the planned 41% by July 2, 2026. Key areas like the hopper, conveyor system, and screen are significantly advanced, though magnetic separation and electrical works are ongoing. The company maintains its target for operational readiness by the end of August 2026, contingent on completing remaining tasks and receiving the Operating Licence, for which workstreams are progressing as expected. Cadence's total investment in the Amapá Project stands at approximately US$16.1 million, representing a 36.2% equity stake.

Disclaimer*

UK 100

Latest directors dealings