Azteca Cold and Wet Commissioning Underway

Summary by AI BETAClose X

Cadence Minerals plc has announced that cold and wet commissioning are underway at the Azteca processing plant for the Amapá Iron Ore Project, following mechanical completion. The Amapá State Environmental Secretariat has completed its site inspection without raising any issues, and the company awaits their response before proceeding to hot commissioning, which will test the plant at 25%-50% capacity. Successful commissioning and the subsequent grant of the Azteca Operating Licence are expected to lead to full production, generating initial cash flow for Cadence, which has invested approximately US$16.1 million in the Amapá Project and holds a 36.2% equity interest in the operating entity.