
![]() |
The company deems the information contained within this announcement to constitute Inside Information as stipulated under the Market Abuse Regulation (E.U.) No. 596/2014, as it forms part of U.K. domestic law under the European Union (Withdrawal) Act 2018, as amended. Upon the publication of this announcement via a regulatory information service, this information is considered to be in the public domain.
Cadence Minerals Plc
("Cadence Minerals", "Cadence", or "the Company")
Amapá Project Update - Azteca Plant Progress and Licensing Update
Detailed engineering completed and execution package now in place at Azteca, with early works due to commence in March as key Installation Licence workstreams continue to advance.
Cadence Minerals plc (AIM: KDNC) is pleased to provide an update on progress at the Azteca Plant within the Amapá Iron Ore Project in Brazil ("Amapá" or the "Project"), together with progress on the remaining workstreams associated with the Project's Installation Licence ("LI").
Highlights
· Execution package in place: procurement requests for critical refurbishment items were launched in March 2026, with contractor mobilisation readiness established for a 90-day execution programme.
· Early works commencing: certain permitted preparatory activities are scheduled to commence in March, enabling selected workstreams to progress ahead of the main refurbishment programme.
· Critical path supported: together, these steps are intended to add flexibility across key execution activities and help preserve the current development timetable.
· Licensing workstreams progressing: remaining Installation Licence requirements, including IPHAN, water abstraction and tailings-related permitting, continue to advance in parallel.
· The Azteca plant remains a key component of Cadence's phased redevelopment strategy at Amapá,
Kiran Morzaria, Chief Executive Officer of Cadence Minerals, commented:
"Completion of the detailed engineering studies marks an important step in moving Azteca towards refurbishment and recommissioning. The work programme is now supported by an active procurement and mobilisation package, with procurement requests already launched for critical refurbishment items and the contractor team prepared for mobilisation."
"This is important because it moves Azteca beyond engineering readiness and into practical execution planning, while adding flexibility to the critical path as the remaining Installation Licence workstreams continue to progress. Subject to permitting and execution, Azteca remains central to our phased redevelopment strategy at Amapá, with commissioning targeted by the end of June."
Azteca Plant Advancement
Following the grant of the Preliminary Licence announced on 6 January 2026, Amapá has adopted a structured approach to progressing those activities at Azteca that can be undertaken ahead of the main refurbishment programme.
The detailed mechanical and electrical engineering studies for the Azteca Plant have now been completed. In parallel, the Azteca work programme is now supported by an active procurement and mobilisation package, with critical refurbishment items already requested and contractor mobilisation planning aligned to the execution schedule.
Planned early activities include structural steel repairs, removal of motors, pumps and other components for refurbishment, and procurement of long-lead items required for recommissioning. Certain of these activities are scheduled to commence in March. These activities fall within the scope of works permitted before LI issuance, including maintenance, preservation, inspection, component removal for off-site repair and long-lead procurement.
Together, these steps are intended to add flexibility to the critical path and help preserve the current development timetable, with commissioning targeted for the end of June, subject to receipt of the required permits and execution.
Installation Licence Progress
As previously outlined, following the grant of the Preliminary Licence ("LP") announced on 6 January 2026, progression to the Installation Licence remains subject to completion of defined technical and regulatory requirements. The principal remaining items include: (i) archaeological clearance from the Instituto do Patrimônio Histórico e Artístico Nacional ("IPHAN"), (ii) water abstraction permitting, and (iii) tailings-related permitting to be issued by the State of Amapá environmental authority, the Secretaria de Estado do Meio Ambiente ("SEMA/AP").
Late last year, the Company submitted the archaeological report recommended by the State IPHAN branch to Federal IPHAN. The report evaluates previously identified archaeological locations and concludes that, in several cases, no further study is required or that additional work is not possible due to historic mining activity or areas now covered by legacy tailings or waste material. The Company continues to engage constructively with Federal IPHAN as part of the LI process.
With respect to the SEMA/AP workstreams, a technical inspection was conducted recently, following which SEMA/AP requested a minor amendment to the relevant application. That amendment has now been incorporated, submitted, and is being reviewed by SEMA/AP.
Strategic Context
As previously announced, Cadence and its partners have established a funding structure to support licensing, refurbishment, and initial working capital for the Azteca Plant. The Company continues to view Azteca as the first stage of its broader redevelopment strategy at Amapá.
Subject to receipt of the required licences, recommissioning of Azteca is intended to provide an initial production platform and near-term operational cash flow, while supporting the continued advancement of the wider 5.5 Mtpa DR-grade development.
Cadence Ownership
As of the end of December 2025, Cadence's total investment in the Amapá Project is approximately US$15.5 million, representing a 35.9% equity stake.
About the Amapá Project
The Amapá Iron Ore Project is a fully integrated iron ore operation in Brazil with established mine, rail, port and beneficiation infrastructure. The Project hosts a JORC-compliant Mineral Resource of 276 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe.
An updated Pre-Feasibility Study confirmed the potential to produce 67.5% Fe direct reduction ("DR") grade concentrate at 5.5 Mtpa, with a post-tax NPV (10%) of US$1.97 billion over a 15-year mine life.
As part of a staged redevelopment strategy, Azteca is intended to be recommissioned as the initial production facility, targeting approximately 380,000 tonnes per annum of ~65% Fe concentrate from existing tailings. This initial production is intended to generate early cash flow to support ongoing operations and the broader development of the Project, subject to permitting.
|
For further information, contact:
|
|
|
Cadence Minerals plc |
+44 (0) 20 3582 6636 |
|
Andrew Suckling |
|
|
Kiran Morzaria |
|
|
|
|
|
Zeus (NOMAD & Broker) |
+44 (0) 20 3829 5000 |
|
James Joyce |
|
|
Darshan Patel |
|
|
|
|
|
Fortified Securities - Joint Broker |
+44 (0) 20 3411 7773 |
|
Guy Wheatley |
|
|
|
|
|
Brand Communications |
+44 (0) 7976 431608 |
|
Public & Investor Relations |
|
|
Alan Green |
|
Qualified Person
Kiran Morzaria B.Eng. (ACSM), MBA, has reviewed and approved the information contained in this announcement. Kiran holds a Bachelor of Engineering (Industrial Geology) from the Camborne School of Mines and an MBA (Finance) from CASS Business School.
Cautionary and Forward-Looking Statements
Certain statements in this announcement are or may be deemed to be forward-looking statements. Forward-looking statements are identified by their use of terms and phrases such as "believe", "could", "should", "envisage", "estimate", "intend", "may", "plan", "will", or the negative of those variations or comparable expressions, including references to assumptions. These forward-looking statements are not based on historical facts but rather on the Directors' current expectations and assumptions regarding the company's future growth, results of operations, performance, future capital, and other expenditures (including the amount, nature, and sources of funding thereof), competitive advantages, business prospects and opportunities. Such forward-looking statements reflect the Directors' current beliefs and assumptions and are based on information currently available to the Directors. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements, including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes, actions by governmental authorities, the availability of capital markets reliance on key personnel uninsured and underinsured losses and other factors many of which are beyond the control of the company. Although any forward-looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions. The company cannot assure investors that actual results will be consistent with such forward-looking statements.