Amapá Project Update

AI SummaryClose X

Cadence Minerals Plc has provided an update on the Amapá Project, confirming that detailed engineering for the Azteca Plant is complete and an execution package is in place, with early works scheduled to commence in March 2026. Procurement requests for critical refurbishment items have been launched, and contractor mobilization is ready for a 90-day program. Licensing workstreams, including IPHAN, water abstraction, and tailings permitting, are also advancing. The company's total investment in the Amapá Project as of December 2025 was approximately US$15.5 million, representing a 35.9% equity stake. Commissioning of the Azteca plant is targeted for the end of June, subject to permitting and execution.

Disclaimer*

UK 100

Latest directors dealings