Update - United Kingdom Group Action

Summary by AI BETAClose X

BHP Group Limited has been found liable by the English High Court under Brazilian law for the 2015 Fundão dam failure, with damages to be assessed in future trials expected by 2028 or 2029; BHP intends to appeal this decision. The company highlights that over 610,000 people in Brazil have already been compensated, including approximately 240,000 claimants from the UK group action who have provided releases, which should reduce the value of the UK claims. BHP believes the UK action is duplicative of existing remediation and compensation efforts, including a US$32 billion agreement with Brazilian authorities. Expected cash outflows for Samarco remain largely aligned with previous forecasts of US$2.2 billion for FY2026 and US$0.5 billion for FY2027, with approximately US$1 billion already spent in FY2026. BHP estimates an aggregate provision of US$5.5 billion at 31 October 2025 for its obligations.