BHP Group Limited has updated the market on its Jansen Stage 1 Potash Project, increasing the total investment estimate to US$8.4 billion, up from the previously guided US$7.0 billion to US$7.4 billion range and the initial US$5.7 billion estimate. First production is now scheduled for mid-2027, reverting to the original timeline. These increases are attributed to inflation, design changes, and lower productivity. Despite these adjustments, the project is 75% complete and expected to produce approximately 4.15 million tonnes per annum, with an updated internal rate of return of 7.9% to 9.1% and strong underlying EBITDA margins of 63% to 64%. BHP is also advancing Stage 2 construction and plans to provide an investment expenditure estimate for it in Q4 FY2026.