Hope and Gorob Project commencement of blasting

Summary by AI BETAClose X

Bezant Resources PLC has successfully completed its first blast at the Hope open pit site within its 90% owned Hope & Gorob copper gold project in Namibia, liberating approximately 2,000 tonnes of commercially viable mineralisation from a 20,000 tonne blast. Preliminary evaluations indicate the surface mineralisation is consistent with the geological block model, and the company's grade control team will now compare assays from blasthole sampling with the current surface expression. Mining and transport of run of mine ore to the Tsaoxaub Metals flotation plant will commence shortly to generate a stockpile for future plant commissioning, with the plant site manager onboarded and operator recruitment ongoing.