Publication of a Prospectus and Project Update

AI SummaryClose X

Bazalgette Finance plc has published a prospectus for its £10,000,000,000 multicurrency bond issuance programme and provided an update on the Thames Tideway Tunnel project. The project achieved Handover in August 2026, transferring operational responsibility to Thames Water, but System Acceptance is now expected between February and August 2028 due to weather-related delays impacting commissioning. Ofwat will not impose financial penalties for this delay, and discussions are underway regarding regulatory framework amendments, including potential increases to funding. The company's revised cost estimate remains £4.7bn as of 31 August 2026, and the project has diverted over 21 million cubic metres of sewage from the River Thames.