BKM Copper Project Limestone Drilling Update

AI SummaryClose X

Asiamet Resources provided an update on its limestone resource drilling program at the Rinjen prospect. The drilling program is currently 50% complete, with all six holes drilled intersecting limestone at the target depth of 50m. Early assay results from the first two holes confirm high-quality limestone, exceeding 54% Calcium Oxide (CaO) as measured by XRF, equating to a limestone quality exceeding 95%. The company anticipates completing the 12-hole program by mid-October.