Quarterly Activities Report 31 December 2025

Summary by AI BETAClose X

Ariana Resources plc reported significant progress for the quarter ended December 31, 2025, highlighted by a binding agreement with Hongkong Xinhai Mining Services Ltd. for A$8 million in immediate funding and up to A$3 million for metallurgical work and the Dokwe Gold project's Definitive Feasibility Study in Zimbabwe, alongside a year-end cash balance of approximately £5.4 million. The company commenced an RC drilling campaign at Dokwe for resource expansion and reported initial positive intercepts, while heap-leach operations at the Tavşan Gold Mine in Türkiye began with a first doré pour of 13.4kg, contributing to record total revenue of US$71.8 million from 19,517 oz gold and silver from Zenit Mining operations. Resource and exploration drilling continued at Tavşan, with a revised Mineral Resource Estimate expected in Q2 2026, and infill drilling at the Kizilcukur deposit in Türkiye also yielded promising results.

Disclaimer*

Ariana Resources PLC
30 January 2026
 

 

Ariana Resources PLC NEW

Quarterly Activities Report for the quarter ended 31 December 2025

Ariana Resources plc (AIM: AAU, ASX: AA2, "Ariana" or the "Company"), the mineral exploration, development and production company with gold project interests in Africa and Europe, provides the quarterly activities report for the quarter ended 31 December 2025.

Highlights:

·   Binding Definitive Agreement was signed with Hongkong Xinhai Mining Services Ltd. ("Xinhai") to provide A$8 million in immediate funding, and up to a further A$3 million (payable in equity) for a metallurgical sampling and testwork programme and to progress the Definitive Feasibility Study at the Dokwe Gold project in Zimbabwe; cash balance of the Company at year end was c.£5.4 million.

·    Initial 26-hole reverse circulation ("RC") drilling campaign for c.4,000m targeting resource expansion currently underway at Dokwe. Key intercepts (from DRC9) include:

§ 4m @ 1.98g/t Au from 188m

§ 9m @ 1.33g/t Au from 194m

§ 11m @ 1.37g/t Au from 206m

§ 14m @ 2.17g/t Au from 220m, including 6m @ 4.15g/t Au from 220m

 

Heap-leach operations at the Tavşan Gold Mine in Türkiye commenced with the first doré pour of 13.4kg of gold-silver produced in early December, with record total revenue from Zenit Mining (Kiziltepe and Tavşan), achieving US$71.8 million from 19,517 oz gold (plus silver).

·    Resource and exploration diamond drilling programme continued at the Tavşan Gold Mine in Türkiye, with 12,206m completed of an overall c.15,000m drill programme, with a revised Mineral Resource Estimate expected in Q2 2026.

·    71 holes for 5,345m at the Tavşan North Zone completed. Key intercepts include:

§ 5.10m @ 7.23g/t Au + 3.61g/t Ag from 76.0m           (TAV-D002-25)

§ 8.50m @ 3.70g/t Au + 2.09g/t Ag from 50.7m           (TAV-D138B-25)

§ 7.30m @ 4.02g/t Au + 4.81g/t Ag from 35.8m           (TAV-D045-25)

including 1.00m @ 21.54g/t Au + 8.31g/t Ag from 41.5m

·    85 holes for 3,887m at the Tavşan Main and South Zones also completed. Key intercepts include:

§ 15.7m @ 1.51g/t Au + 7.82g/t Ag from surface         (TAV-D014-25)

§ 7.4m @ 2.76g/t Au + 3.10g/t Ag from 16.9m             (TAV-D030A-25)

§ 9.7m @ 1.91g/t Au + 3.27g/t Ag from 0.8m               (TAV-D079-25)

 

·    Diamond drilling programme of 31 holes for 2,769m completed at the Kizilcukur deposit in Türkiye for infill drilling, and to test for potential extension zones. The best intercepts include:

§ 4.90m @ 4.53g/t Au + 118.3g/t Ag from 24.4m         (KCR-D07-25)

§ 3.60m @ 2.89g/t Au + 77.5g/t Ag from 59.3m           (KCR-D19-25)

§ 1.90m @ 5.39g/t Au + 70.6g/t Ag from 66.1m           (KCR-D21-25)


Dr. Kerim Sener, Managing Director, commented:

"The last quarter has seen tremendous activity for the Company across its flagship Dokwe Gold Project in Zimbabwe and its other project interests in Türkiye. Notably, we commenced our RC exploration drilling programme at Dokwe and continued to receive excellent drilling results from the ongoing diamond drilling programme at the Tavşan Mine and Kizilcukur Deposit in Türkiye.


"Furthermore, the period marked the commencement of commercial operations at the Tavşan Mine following the completion of the heap-leach pads and the loading of the first ore. Recording the first gold-silver pour from the Tavşan Mine was yet another major milestone achieved for the period and indeed for what has been an extraordinary year of progress for the Company. In addition, production revenue from the Kiziltepe and Tavşan mines achieved a record of US$71.8 million as a result of the increasing gold and silver price environment.


"The nature and scope of these activities have not gone unnoticed by the broader market, and during the period, we continued to receive significant strategic investor interest in the Company and our flagship Dokwe Project specifically. This ultimately culminated in the completion of our agreement with the Xinhai Group to help drive the Dokwe Project through to the completion of its Definitive Feasibility Study, scheduled for later this year. The speed and efficiency with which we completed this deal bodes well for our ongoing relationship with Xinhai and the delivery of further project milestones."


Dokwe Gold Project, Zimbabwe

The Company holds a 100% interest in the Dokwe Project, which represents one of the most significant gold projects in Zimbabwe and is Ariana's flagship growth project. The project hosts a substantial in-pit JORC-compliant mineral resource estimate of 1.4Moz of gold (Table 1) with a robust grade profile and hosts significant exploration upside across the broader licence area.

 

Soil Sampling Programme

In early October, the Company completed a soil geochemical programme comprising a total of 10,086 soil samples. The samples had been collected for multi-element portable XRF ("pXRF") on a 50m by 100m grid across the entire project area, totalling 44km2, and of these, a selection was analysed for gold using detectORETM. This work, in addition to an extensive assessment and re-processing of the previous geological, geophysical and geochemical data, has resulted in a much-improved understanding of the distribution of gold mineralisation at Dokwe North and Central.

 

A review of the samples has led to several new target areas being defined or known target areas further refined. An RC drilling programme has been planned to test some of the highest priority targets. These include near-mine extensional targets and several regional exploration targets.

 

For further information, please see the AIM announcement on 23 October 2025 and an addendum on the ASX on 27 October 2025.

 

Drilling Programme

During the quarter, the Company commenced the first phase of an overall c.11,000m drilling programme planned across Dokwe North and Dokwe Central and their extensions.

 

Four initial target areas are being tested in an initial 26-hole, c.4,000m RC drilling campaign designed to identify potential areas for future resource expansion (Figure 1). These four targets comprise:

§ Dokwe Northeast extension target - where the soil sampling programme had identified a coincident gold and arsenic anomaly to the north east of the Dokwe deposit.

§ Dokwe Central Western extension target - where a reinterpretation of historical drilling indicates that the Central Shear Zone and the mineralisation appear to have been faulted southwards at the western end of the resource.

§ Sinkwe Prospect - located approximately 750m eastwards from Dokwe Central along the Central Shear Zone, where a historical drill hole, DPD4, intercepted 7.3m @ 6.63g/t Au from 32.2m depth.

§ Siduli Pan Prospect - located approximately ~2.5km southeast of Dokwe Central, where a historical hole, DSD02, intercepted 0.5m @ 81.09g/t Au from 243m depth.

 

A map of a mountain range AI-generated content may be incorrect.

Figure 1: Summary map showing locations of all RC drill holes completed to date and the additional drilling positions expected to be utilised as the programme continues

 

By the year-end camp closure, the Company had completed 3,317 metres of RC drilling across 18 holes.

 

The results from drill hole DRC9 were prioritised in the laboratory, with the results of the other holes still pending as of year-end. DRC9 was drilled southwards through the Dokwe Central Resource, testing for continuity of mineralisation between the North Zone and the South Zone (Figure 2), and now confirms the South Zone remains open further to the south.

 

The key intercepts from DRC9 were:

4m @ 1.98g/t Au from 188m

9m @ 1.33g/t Au from 194m

11m @ 1.37g/t Au from 206m

14m @ 2.17g/t Au from 220m, including 6m @ 4.15g/t Au from 220m

 

A map of a geological study AI-generated content may be incorrect.

Figure 2: Plan view of the Dokwe Central deposit, highlighting the faulted offset of the geology. The drilling target areas occur along the southern continuation of the South Zone on the east side of the fault, and the displaced geology on the west side (Note: 'py' refers to pyrite)

 

The scale and grade of the intercepts from the first hole drilled beyond the current resource in this area provide encouragement that the resource can be increased, and Ariana looks forward to following up on these results in early 2026.

 

For further information, please see the AIM announcements on 23 October 2025, 4 November 2025, 12 December 2025 and 23 December 2025, as well as the addendum on the ASX on 27 October 2025.

 

Türkiye Projects

Ariana has a 23.5% interest in the Kiziltepe Gold-Silver Mine, the Tavşan Gold Mine and the Salinbaş-Ardala Project located in Türkiye through its holding in Zenit Mining Operations ("Zenit"). Ariana's partners, Proccea Construction Co. (23.5%), manage the operations, with the remaining 53% held by Özaltin Holding A.Ş.

 

In Q4 2025, Zenit had produced and sold 6,560 ounces of gold and 20,205 ounces of silver for US$28.2 million in revenue from its combined Kiziltepe and Tavşan operations. Revenue for the year reached a record (US$71.8 million), as a result of the higher gold price environment from production, which achieved 19,517 ounces of gold and 70,673 ounces of silver for 2025. This production represents the upper end of the range provided in Q4 2025.

 

Kiziltepe Gold-Silver Mine

The Kiziltepe Gold-Silver Mine commenced operations in 2017 and has delivered multiple years of profitable production from its CIL plant, including the payment of dividends to its shareholders from 2018 through to early 2021. Since then, cash flow from the mine has largely funded the development of a second operation for Zenit at the Tavşan Gold Mine. Operations at Kiziltepe continued with the processing of both Kiziltepe and Tavşan ore throughout the period.

 

During the quarter, the Company completed a diamond drilling ("DD") programme at the Kizilcukur Deposit, located 22km northeast of the Kiziltepe mine. Kizilcukur is being advanced towards providing satellite ore feed to the producing Kiziltepe Gold-Silver Mine.

 

The DD programme at Kizilcukur comprised 31 drill holes for a total of 2,769 metres and was primarily designed to provide step-out drilling along the north-western and south-eastern extents of the existing resource areas, and to test identified potential extension zones.

 

The best intercepts from the programme were:

4.90m @ 4.53g/t Au + 118.3g/t Ag from 24.4m   (KCR-D07-25)

3.60m @ 2.89g/t Au + 77.5g/t Ag from 59.3m     (KCR-D19-25)

1.90m @ 5.39g/t Au + 70.6g/t Ag from 66.1m     (KCR-D21-25)

 

For further information, please see the AIM announcement on 27 November 2025.

 

Tavşan Gold Mine

The Tavşan Gold Mine contains a JORC 2012 Mineral Resource of 311,000 ounces of gold and 1.1 million ounces of silver and an associated Mineral Reserve, underpinning a potential eight-year total mine life (Tables 2 and 3).

 

Drilling Programme

A resource and exploration diamond drilling programme is ongoing, having completed 12,206m for 207 holes by the end of Q4 2025, of an up to 15,000m programme and testing the potential for increases in the life of mine.

 

The programme includes infill holes to aid mine planning but also drilling around the periphery of the currently defined resources, with mineralisation now confirmed to extend beyond the current resource outlines, both at depth and along strike.

 

During the quarter, the Company released the assay results for the 71-hole drilling programme at the Tavşan North Zone. The results from this 5,345m programme included the following best intercepts:

5.10m @ 7.23g/t Au + 3.61g/t Ag from 76.0m     (TAV-D002-25)

8.50m @ 3.70g/t Au + 2.09g/t Ag from 50.7m     (TAV-D138B-25)

7.30m @ 4.02g/t Au + 4.81g/t Ag from 35.8m     (TAV-D045-25)

including 1.00m @ 21.54g/t Au + 8.31g/t Ag from 41.5m

 

The infill drilling in the North Zone has confirmed the continuity of the high-grade domain, as previously modelled. Gaps in the previous model have also been drilled and have intercepted mineralisation at the expected depths.

 

Subsequent to the end of the quarter, the Company released the results of 3,887m of drilling across 85 holes at the Tavşan Main and South Zones. The results included the following key intercepts:

 

15.7m @ 1.51g/t Au + 7.82g/t Ag from surface   (TAV-D014-25)

7.4m @ 2.76g/t Au + 3.10g/t Ag from 16.9m       (TAV-D030A-25)

9.7m @ 1.91g/t Au + 3.27g/t Ag from 0.8m         (TAV-D079-25)

 

The infill drilling in the Main Zone has also confirmed the continuity of the high-grade domain, as previously modelled, whilst the results from the South Zone indicate significant potential to extend mineralisation and expand the resource.

 

A JORC Resource update will be completed at the end of the 15,000m programme at Tavşan and is currently expected in Q2 2026.

 

For further information, please refer to the AIM announcements on 13 November 2025 and 21 January 2026.

 

Mining Operations

Mining commenced in early 2024 at the Tavşan Main Zone, with high-grade ore being trucked to the Kiziltepe Mine for processing through the CIL plant and lower-grade ore being stockpiled at the Tavşan Mine site, in preparation for the commencement of heap-leaching operations. Trucking operations of high-grade ore have continued to the Kiziltepe CIL processing plant until Q1 2026 to benefit from the higher gold recovery inherent to the CIL plant.

 

The heap-leach processing of lower-grade ore commenced at the Tavşan mine site in early October following the receipt of the final permitting for commercial operations. In early December, the Company reported that the first doré pour of 13.4kg of gold-silver had been produced on-site at the Tavşan Mine.

 

Zenit has already spent two years mining and stockpiling run-of-mine ore at Tavşan; the operation is in excellent shape to ramp up to full-scale operations through the Spring. The heap-leach pad is currently loaded with c.135,000 tonnes of ore, with a further c.750,000 tonnes of stockpiled ore being prepared for loading over the next year.

 

For further information, please see the AIM announcements on 8 October 2025 and 3 December 2025.

 

Salinbaş Gold-Silver Project

The Salinbaş Gold-Silver Project is in north-eastern Türkiye, comprising two primary areas of differing, although related mineralisation, Salinbaş and Ardala, located across two adjacent licences held by Zenit. A third contiguous licence, located further to the south, contains the Hizarliyayla Gold Prospect.

 

A drilling programme commenced at the Salinbaş gold-silver deposit, the Ardala Zone and at Hizarliyayla during late 2021 and is currently paused with a restart expected in due course. On completion of the drilling programme, the Company expects to revise its Mineral Resource Estimate.

 

South-east European Projects

The Company has several projects in Cyprus through its 61% interest in Venus Minerals Limited ("Venus"). The most advanced of these is the Magellan Project. Magellan represents a cluster of copper-gold-silver-zinc volcanogenic massive sulphide deposits, with scoping and pit-optimisation studies previously completed. Outside of this project area, Venus holds various other tenements, including those at its Mariner Project, which represents a series of walk-up drill targets with visible copper mineralisation at surface.

 

During the quarter, Venus continued to maintain its tenements in good standing through the completion of the appropriate geological work and periodic reporting to the Mines Service of Cyprus.

 

The Company has several licence applications in process in Kosovo through its 76% interest in Western Tethyan Resources ("WTR"). WTR in turn owns 51% of the Slivova Project*, which is a gold-silver deposit located in central Kosovo, within an underexplored but well-mineralised belt with proven endowment. Slivova is expecting to advance through further technical studies, with the project showing strong potential to become a near-term development opportunity.

 

The Company also has an Exploration Alliance with Newmont Mining Corporation, with Newmont having committed US$3.3 million in capital to date to the exploration programmes of WTR via its investment in Ariana.

 

* WTR applied for a new exploration licence over the Slivova Project in May 2025, which remains pending with the Independent Commission for Mines and Minerals in Kosovo. Refer to the Company's replacement prospectus dated 5 August 2025 for further details.

 

Corporate

 

Xinhai Funding Agreement

The Company announced on 22 December 2025 that it had entered into a binding Definitive Agreement with Hongkong Xinhai Mining Services Ltd (part of Shandong Xinhai Mining Technology & Equipment Inc.) to provide A$8 million in immediate funding and to conduct a Metallurgical Sampling and Testwork Programme and to progress the Definitive Feasibility Study ("DFS") at the Dokwe Gold Project in Zimbabwe.

 

The key terms of the investment are:

§ Xinhai to make an A$8 million equity investment to be completed in Ariana CDIs at a price of A$0.30 per CDIs ("Tranche 1").

§ Xinhai will also provide technical services in relation to a Metallurgical Sampling and Testwork Programme for A$1 million ("Tranche 2") and for a DFS at Dokwe, under the management of Ariana, for up to A$2 million ("Tranche 3") to be paid in CDIs at the Issue Price.

§ Xinhai to be granted up to 18,333,333 options to acquire CDIs on a 1 option per 2 CDI issued basis with each option having an exercise price of A$0.50 per CDI, exercisable until 31 December 2027, as follows:

-      upon completion of Tranche 1 of the Investment, 13,333,333 CDI Options;

-      upon completion of Tranche 2 of the Investment, 1,666,667 CDI Options; and

-      upon completion of Tranche 3 of the Investment, up to 3,333,333 CDI Options.

§ Xinhai to nominate one member to the Ariana board on satisfaction of certain conditions in the Definitive Agreement.

 

The Company subsequently issued 26,666,667 Tranche 1 CDIs on 30 December 2025 using the available placement capacity under Listing Rule 7.1.

 

Shareholder approval, however, is required for the issue of the Tranche 2 CDIs (3,333,333), the Tranche 3 CDIs (6,666,667) and for each of the three tranches of the CDI Options.

 

A general meeting of shareholders will be held in London on 25 February 2026.

 

For further information, please see the AIM announcement on 22 December 2025.

 

Listing Rule Disclosures

 

Exploration Expenditure

In accordance with ASX Listing Rule 5.3.1, the Company spent £571,000 on exploration work during the quarter, which largely comprised the drilling campaign and associated costs at the Dokwe Gold Project, Zimbabwe.

 

Mining Production and Development Expenditure

In accordance with ASX Listing Rule 5.3.2, there were no substantive mining production and development activities or expenditure during the quarter. The Company notes that production and development expenditure incurred by Zenit in relation to the Türkiye Projects are not included within the Appendix 5B Cash Flows, as Zenit is not considered to be a subsidiary of the Group.

 

Tenement Information

In accordance with ASX Listing Rule 5.3.3, the Company advises the following:

(1)  During the quarter, there were no tenements acquired or disposed of;

(2)  The mining tenements held by the Company as of 31 December 2025 are set out in the table overleaf;

(3)  There were no new farm-in or farm-out agreements entered into during the quarter; and

(4)  The Company held no beneficial percentage interests in farm-in or farm-out agreements as at the end of the quarter.

 

Use of Funds

In accordance with ASX Listing Rule 5.3.4, a comparison of the Company's actual cash expenditure since listing against the "use of funds" statement outlined in the Pre-Quotation Disclosure is included below:

 

Allocation of Funds

One Year Use of Funds, per Pre-Quotation Disclosure dated 8 September 2025

Current Quarter Expenditure

(Oct-Dec 2025)

Year to Date Expenditure

(since listing)

$A ('000,000)

£ ('000,000)1

£ ('000,000)

£ ('000,000)

Feasibility Study: Dokwe Project

1.0

0.5

0.0

0.0

Drilling Programme: Dokwe Project

2.5

1.2

0.5

0.6

Slivova Gold-Silver Project

0.4

0.2

-

-

Funding of Western Tethyan Alliance

0.4

0.2

0.1

0.1

Funding of Venus Minerals

0.2

0.1

0.0

0.0

Part repayment of RiverFort Facility (including reprofiling fee) prior to Admission

1.9

0.9

-

0.9

Part repayment of RiverFort Facility in the 12 months following Admission

1.5

0.7

0.3

0.3

Working capital and corporate administration costs

2.0

1.0

0.8

1.2

Expenses of the Public Offer

1.5

0.7

0.3

0.8

TOTAL

11.4

5.5

2.0

3.9

 1 Exchange rate used on date of Pre-Quotation Disclosure announcement on 8 September 2025 [A$1:£0.4865]

 

During the quarter, there were no material variances requiring explanation, noting that the Company was listed in September 2025.

 

Payments to Related Parties

In accordance with ASX Listing Rule 5.3.5, the Company advises that the payments to related parties of the Company and their associates, as advised in the Appendix 5B, for the quarter ended 31 December 2025 were £239,000 for related Directors' fees, accounting and company secretarial related services.

 

Schedule of Tenements

Country

District

Company/Holder

License Name

License ID

Type

Status

Ariana Ownership %

Zimbabwe

Bulawayo

Canister Resources

Dokwe

81 contiguous gold claims

Mining Rights

Granted

100

Zimbabwe

Bulawayo

Canister Resources

Dokwe

22 copper-base metal claims

Mining Rights

Granted

100









Kosovo

NE Kosovo

Western Tethyan Resources

Hertica

Re-application

Exploration

Pending

76

Kosovo

NE Kosovo

Western Tethyan Resources

Orllan

Application

Exploration

Pending

76

Kosovo

NW Kosovo

Western Tethyan Resources

Paruci

Application

Exploration

Pending

76

Kosovo

North Kosovo

Western Tethyan Resources

Bistrica

Application

Exploration

Pending

76

Kosovo

Central Kosovo

Western Tethyan Resources

Gjilan

Application

Exploration

Pending

76

Kosovo

Central Kosovo

Western Tethyan Resources

Slivova

Re-application

Exploration

Pending

39









Cyprus

North Troodos

Venus Minerals

New Sha

PP4715

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Pitharochoma

PP4793

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Kalo Chorio South

PP4846

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Kokkinoyia East

PP4850

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Avdellero

PP4704

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Ayios Theodoros West

PP4851

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Ayia Marina

PP4784

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

West Skouriotissa

PP4783

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Klirou West

PP4789

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Klimata

PP4787

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Troulli South

PP4786

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Klirou

PP4794

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

West Nikitari

PP4795

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Margi

PP4828

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Troulli East

PP4893

Exploration

Granted

61

Cyprus

North Troodos

Venus Minerals

Klirou Far East

PP4891

Exploration

Granted

61

Cyprus

North Troodos

Red Metals

North Klirou

AE4940

Exploration

Granted

0 *

Cyprus

North Troodos

Red Metals

Kokkinoyia

AE4938

Exploration

Granted

0 *

Cyprus

North Troodos

Red Metals

North Alestos

AE4939

Exploration

Granted

0 *









Turkiye

Kutahya

Zenit

Orencik

12743

Production

Granted

23.5

Turkiye

Kutahya

Zenit

Evciler

72400

Production

Granted

23.5

Turkiye

Kutahya

Zenit

Kavakli

59770

Production

Granted

23.5

Turkiye

Kutahya

Zenit

Simav

70484

Production

Granted

23.5

Turkiye

Balikesir

Zenit

Umurlar

44828

Production

Granted

23.5

Turkiye

Balikesir

Zenit

Yolcupinar

44830

Production

Granted

23.5

Turkiye

Balikesir

Zenit

Coturtepe

20065879

Production

Granted

23.5

Turkiye

Balikesir

Zenit

Ivrindi

68474

Production

Granted

23.5

Turkiye

Balikesir

Zenit

Kizilcukur

200700970

Production

Granted

23.5

Turkiye

Bilecik

Zenit

Bilecik

202001342

Exploration

Granted

23.5

Turkiye

Artvin

Zenit

Ardala

65842

Production

Granted

23.5

Turkiye

Artvin

Zenit

Salinbas

201300658

Production

Granted

23.5

Turkiye

Artvin

Zenit

Hizarliyayla

201300659

Production

Granted

23.5









* Access Agreement between Venus Minerals and Red Metals - it is anticipated that the beneficial interest may match Ariana's 61% ownership of Venus Minerals if certain future agreements are completed


Table 1 - Dokwe Mineral Resource Estimate

PROJECT

CLASSIFICATION

(REPORTING CUT-OFF GRADE 0.3g/t Au)

TONNAGE
(t)

GRADE
(g/t Au)

CONTAINED GOLD (oz)

Dokwe North

Measured

17,309,000

1.06

592,000

Indicated

18,562,000

0.90

537,000

Inferred

7,095,000

0.82

187,000

Total

42,966,000

0.95

1,316,000

Dokwe Central

Indicated

1,811,000

1.60

93,000

Inferred

120,000

1.69

7,000

Total

1,931,000

1.61

100,000

Total

Measured

17,309,000

1.06

592,000

Indicated

20,373,000

0.96

631,000

Inferred

7,214,000

0.83

193,000

TOTAL

44,896,000

0.98

1,416,000

 

PROJECT

CLASSIFICATION

(REPORTING CUT-OFF GRADE 0.6g/t Au)

TONNAGE
(t)

GRADE
(g/t Au)

CONTAINED GOLD (oz)

Dokwe North

Measured

10,220,000

1.50

493,000

Indicated

8,260,000

1.50

399,000

Inferred

3,123,000

1.33

134,000

Total

21,604,000

1.48

1,025,000

Dokwe Central

Indicated

1,207,000

2.19

85,000

Inferred

98,000

1.98

6,000

Total

1,306,000

2.18

91,000

Total

Measured

10,220,000

1.50

493,000

Indicated

9,468,000

1.59

484,000

Inferred

3,222,000

1.35

140,000

TOTAL

22,909,000

1.52

1,116,000

 

Notes:

1.  The Dokwe Mineral Resource Estimate is reported in accordance with the JORC Code. Reported using cut-offs grades of 0.3g/t Au and 0.6g/t Au As at 4 March 2025

2.   Refer to sections 4.8.5 and 4.8.6 of the IGR for further information regarding the Dokwe Mineral Resource Estimate including information required by ASX Listing Rule 5.8

3.   The Dokwe Mineral Resource Estimate is inclusive of Reserves

 

Table 2 - Tavşan Mineral Resource Estimate

MINERAL DOMAIN

CLASSIFICATION

TONNAGE
(TONNES)

GRADE

CONTAINED METAL

Au (g/t)

Ag (g/t)

Au (oz)

Ag (oz)

High-grade Domain
Cut-off: 1.5g/t Au

Measured

781,800

2.53

4.32

63,600

108,600

Indicated

286,700

2.46

5.72

22,700

52,700

Inferred

94,600

2.35

5.74

7,100

17,400

TOTAL

1,163,000

2.50

4.78

93,400

178,700

Low-grade Domain
Cut-off: 0.5g/t Au

Measured

2,981,600

1.04

4.86

99,900

466,300

Indicated

2,131,600

1.04

3.89

71,300

266,400

Inferred

1,373,900

1.05

4.37

46,300

192,900

TOTAL

6,487,100

1.04

4.44

217,600

925,700

TOTAL

Measured

3,763,300

1.35

4.75

163,500

574,900

Indicated

2,418,300

1.21

4.10

94,000

319,100

Inferred

1,468,500

1.13

4.46

53,400

210,400

TOTAL

7,650,100

1.26

4.49

311,000

1,104,400

 

Notes:

1.  The Tavşan Mineral Resource Estimate is reported in accordance with the JORC Code. Reported using variable cut-off grades of low domain of 0.5g/t Au and high domain of 1.5g/t Au

2.   The Tavşan Mineral Resource Estimate is reported inclusive of Reserves

3.   Refer to sections 5.6.6 and 5.6.7 of the Independent Geologist's Report (IGR) for further information regarding the Tavşan Mineral Resource Estimate including the information required by ASX Listing Rule 5.8

 

Table 3 - Tavşan Ore Reserve Estimate

CATEGORY

TONNAGE
(MT)

GRADE

CONTAINED METAL

Au (g/t)

Ag (g/t)

Au (oz)

Ag (oz)

Proven

2.5

1.46

5.02

116,400

401,100

Probable

2.0

1.32

4.15

84,600

266,200

TOTAL

4.5

1.40

4.63

200,900

667,300

 

Notes:

1.   The Tavşan Ore Reserves are reported in accordance with the JORC Code. Reported using variable cut-off grades of low domain of 0.5g/t Au and high domain of 1.5g/t Au

2.   Refer to section 5.6.8 of the IGR for further information regarding the Tavşan Ore Reserves including the information required by ASX Listing Rule 5.9


Compliance Statements

The information in this announcement relating to Mineral Resources and Ore Reserves has been reported by the Company in accordance with the 2012 Edition of the 'Australasian Code for Reporting of Exploration results, Mineral Resources and Ore Reserves' (JORC Code) previously (refer to the Company's replacement prospectus which was released to the ASX market platform on 8 September 2025 (Prospectus) and is available on the Company website at http://www.arianaresources.com/) (Previous Market Announcement).

 

The Company confirms that it is not aware of any new information or data that materially affects the information included in the Previous Market Announcement and, in the case of estimates of Mineral Resources and Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the Previous Market Announcement continue to apply and have not materially changed.

 

The information in this announcement that relates to the Dokwe PFS production target, or the forecast financial information derived from that production target was first reported on the ASX in the Previous Market Announcement. The Company confirms that all the material assumptions underpinning the production target, and the forecast financial information derived from the production target, in the Previous Market Announcement continue to apply and have not materially changed.

 

Competent Persons Statements

The information in the Investment Overview Section of the prospectus (included at Section 3), the Company and Projects Overview (included at Section 5), and the Independent Geologist's Report (included at Annexure A of the prospectus), which relate to exploration targets, exploration results, mineral resources, Ore Reserves and forward looking financial information is based on, and fairly represents, information and supporting documentation prepared by Alfred Gillman, Ruth Woodcock, Izak van Coller, Hovhannes Hovhannisyan (together, the JORC Competent People), and Richard John Siddle, Andrew Bamber and Daniel Van Heerdan (together, the Qualified People). Refer to the Independent Geologist's Report for further information in relation to the information compiled by each of the JORC Competent People and the Qualified People, their professional memberships, their relevant qualifications and experience and their relationship with the Company.

 

The information in this announcement relating to Exploration Results at the Dokwe Gold Project is based on, and fairly represents, information and supporting documentation prepared by Mr Zack van Coller BSc (Hons). Mr van Coller is a full-time employee of Ariana Resources plc. Mr van Coller is a Member of the Australian Institute of Mining and Metallurgy, a Fellow of the Geological Society London (a Registered Overseas Professional Organisation as defined in the ASX Listing Rules), and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which has been undertaken to qualify as a Competent Person as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves" (the JORC Code 2012). Mr van Coller consents to the inclusion in this report of the matters based on the information compiled by him, in the form and context in which it appears.

 

The information in this announcement relating to Exploration Results at the Dokwe Gold Project is also based on, and fairly represents, information and supporting documentation prepared by Ms. Ruth Woodcock, Exploration Group Leader, Ariana Resources plc. Ms. Woodcock is a member of Recognised Professional Organisations as defined by JORC 2012: a Chartered Geologist (CGeol, Geological Society of London) and European Geologist (EurGeol, European Federation of Geologists) and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity upon which she is reporting as a Competent Person as defined in the 2012 Edition of "The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves." Ms. Woodcock consents to the inclusion in this report of the matters based on the information compiled by her, in the form and context in which it appears.

 

The information in this announcement relating to Exploration Results at the Kizilcukur Project is based on, and fairly represents, information and supporting documentation prepared by Mr Zack van Coller BSc (Hons). Mr van Coller is a full-time employee of Ariana Resources plc. Mr van Coller is a Member of the Australian Institute of Mining and Metallurgy, a Fellow of the Geological Society London (a Registered Overseas Professional Organisation as defined in the ASX Listing Rules), and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which has been undertaken to qualify as a Competent Person as defined in the 2012 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves" (the JORC Code 2012). Mr van Coller consents to the inclusion in this report of the matters based on the information compiled by him, in the form and context in which it appears.

 

The information in this announcement that relates to Exploration Results at Tavşan is based upon information compiled by Ms. Ruth Woodcock, Exploration Group Leader, Ariana Resources plc. Ms. Woodcock is a member of Recognised Professional Organisations as defined by JORC 2012: a Chartered Geologist (CGeol, Geological Society of London) and European Geologist (EurGeol, European Federation of Geologists) and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity upon which she is reporting as a Competent Person as defined in the 2012 Edition of "The Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves." Ms. Woodcock consents to the inclusion in this report of the matters based on the information compiled by her, in the form and context in which it appears.

 

The Company confirms that the form and context in which the Competent Persons' findings are presented have not been materially modified from the Previous Market Announcements.

 

Forward-looking statements and disclaimer

This announcement contains certain "forward-looking statements". Forward-looking statements can generally be identified by the use of forward looking words such as "forecast", "likely", "believe", "future", "project", "opinion", "guidance", "should", "could", "target", "propose", "to be", "foresee", "aim", "may", "will", "expect", "intend", "plan", "estimate", "anticipate", "continue", "indicative" and "guidance", and other similar words and expressions, which may include, without limitation, statements regarding plans, strategies and objectives of management, anticipated production dates, expected costs or production outputs for the Company, based on (among other things) its estimates of future production of the Projects.

 

To the extent that this document contains forward-looking information (including forward-looking statements, opinions or estimates), the forward-looking information is subject to a number of risk factors, including those generally associated with the gold exploration, mining and production businesses. Any such forward-looking statement also inherently involves known and unknown risks, uncertainties and other factors that may cause actual results, performance and achievements to be materially greater or less than estimated. These factors may include, but are not limited to, changes in commodity prices, foreign exchange fluctuations, general economic and share market conditions, increased costs and demand for production inputs, the speculative nature of exploration and project development (including the risks of obtaining necessary licenses and permits and diminishing quantities or grades of reserves), changes to the regulatory framework within which the Company operates or may in the future operate, environmental conditions including extreme weather conditions, geological and geotechnical events, and environmental issues, and the recruitment and retention of key personnel.

 

- ENDS -

 

The Board of Ariana Resources plc has approved this announcement and authorised its release.

 

For further information on the Company, please visit the website, or please contact the following:

 

Contacts:

 

Ariana Resources plc

Michael de Villiers, Chairman

Dr. Kerim Sener, Managing Director


Tel: +44 (0) 20 3476 2080




Beaumont Cornish Limited

(Nominated Adviser)

Roland Cornish / Felicity Geidt


Tel: +44 (0) 20 7628 3396

 



Zeus Capital (Joint Broker)

Harry Ansell / Katy Mitchell

 

Fortified Securities (Joint Broker)

Guy Wheatley

 

Yellow Jersey PR Limited (UK Financial PR)

Dom Barretto / Shivantha Thambirajah

 

M&C Partners (Aus Financial PR)

Christina Granger / Ben Henri

 

Shaw and Partners Limited

(Lead Manager - ASX)

Damien Gullone

 

 

 

Tel: +44 (0) 203 829 5000

 

 

Tel: +44 (0) 203 411 7773

 

 

Tel: +44 (0) 7983 521 488

arianaresources@yellowjerseypr.com

 

Tel: +61 438 227 286

christina.granger@mcpartners.com.au

 

Tel: +61 (0)2 9238 1268

 

 

 

Beaumont Cornish Limited ("Beaumont Cornish") is the Company's Nominated Adviser and is authorised and regulated by the FCA. Beaumont Cornish's responsibilities as the Company's Nominated Adviser, including a responsibility to advise and guide the Company on its responsibilities under the AIM Rules for Companies and AIM Rules for Nominated Advisers, are owed solely to the London Stock Exchange. Beaumont Cornish is not acting for and will not be responsible to any other persons for providing protections afforded to customers of Beaumont Cornish nor for advising them in relation to the proposed arrangements described in this announcement or any matter referred to in it.

 

About Ariana Resources:

Ariana is a mineral exploration, development and production company dual listed on AIM (AIM: AAU) and ASX (ASX: AA2), with an exceptional track record of creating value for its shareholders through its interests in active mining projects and investments in exploration companies. Its current interests include a major gold development project in Zimbabwe, gold-silver production in Türkiye and copper-gold-silver exploration and development projects in Kosovo and Cyprus.

For further information on the vested interests Ariana has, please visit the Company's website at www.arianaresources.com.

Zeus Capital Limited, Fortified Securities and Shaw and Partners Limited are the brokers to the Company, and Beaumont Cornish Limited is the Company's Nominated Adviser.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 