Ntorya Operations Update

Summary by AI BETAClose X

Aminex reports the Ntorya-3 drilling rig has been contracted and is scheduled to arrive mid-December 2026 with spudding anticipated in late-December 2026; NT-3 civil works are approximately 60% complete and access roads approximately 80% complete with site handover targeted for 15 December 2026. NT-2 wellhead maintenance is complete, bridge-plug removal is expected late-November 2026, testing is scheduled for December 2026 and production into the Ntorya-Madimba pipeline is targeted for late-December 2026. NT-1 maintenance is delayed pending valve delivery, and the pipeline remains on schedule for December 2026 completion.