Ntorya Operations Update

Summary by AI BETAClose X

Aminex PLC has announced an operational update for the Ntorya gas development, with joint venture partners approving work programmes and budgets projecting gross expenditure of up to US$75 million through the remainder of 2026 and 2027. Key activities include the commencement of testing and production from Ntorya-2 in December 2026, with the Ntorya-Madimba pipeline scheduled for completion in the same month. Maintenance on Ntorya-1 is set for October 2026, potentially leading to a delay in its production to December 2027 if a workover is required. Drilling of the Ntorya-Central well is anticipated to spud in December 2026, with potential first gas in September 2027, and options exist for further wells, Ntorya-East and Ntorya-West, dependent on results.

Disclaimer*

Aminex PLC
23 September 2026
 

23 September 2026

AMINEX PLC
("Aminex" or "the Company")

Ntorya Operations Update

Aminex is pleased to provide an operational update on the Ntorya gas development.

Aminex's wholly owned subsidiary, Ndovu Resources Limited ("Ndovu"), and ARA Petroleum Tanzania Limited ("APT"), operator of the Ruvuma PSA, recently met to consider the revised work programme and budget for 2026 and the provisional work programme and budget for 2027. The joint venture approved both work programmes and budgets, with gross expenditure of up to US$75 million projected across the remainder of 2026 and 2027.

 

Ntorya-2 ("NT-2")

The removal of bridge plugs and subsequent testing of NT-2 is scheduled to commence in November 2026, followed by production in December 2026 into the Ntorya-Madimba pipeline. The necessary flowlines will be constructed in parallel and will be completed prior to the commencement of production. The contract for the supply of the gas processing unit ("GPU") is expected to be signed later this month.

 

Ntorya-1 ("NT-1")

Wellhead maintenance and slickline operations on NT-1 are scheduled to commence in October 2026. The results will determine whether further work, including a rig-operated workover, is required. If a workover is required, it will be carried out immediately after the drilling of the Ntorya-Central well, resulting in a delay to gas production from the well to December 2027.

 

Ntorya-Central ("NT-C")

Negotiations are now at a very advanced stage to contract a drilling rig to drill a well at the Ntorya-Central ("NT-C") location. The contract is expected to be signed in October 2026 with the well scheduled to be spudded in December 2026 as Ntorya-3 ("NT-3"). If successful, NT-3 will be tied into the Ntorya development with first gas from the well available in September 2027.

 

Ntorya-East ("NT-E") and Ntorya-West ("NT-W")

Dependent upon the results of the NT-3 well, the joint venture will have the option to drill up to two additional appraisal/development wells - NT-E and NT-W - on a back-to-back basis, following the completion of operations on NT-3 and, if required, NT-1.

 

Chikumbi-1 ("CH-1")

The drilling of CH-1, an obligatory well to be drilled under the terms of the Development Licence and the Farmout Agreement, will be drilled at the end of the above programme.

 

 

Ntorya to Madimba Pipeline ("Pipeline")

The Pipeline is scheduled for completion in December 2026, when it will be ready to transport gas from Ntorya to the Madimba Gas Processing Plant. TPDC has confirmed that approximately 95% of pipelaying and infilling is now complete and the necessary connection and metering works at Madimba are ongoing.

Charles Santos, Executive Chairman of Aminex, commented:

"We are pleased to have reached agreement with APT on the revised 2026 work programme and budget and the provisional 2027 programme, which together envisage an expenditure of up to US$75 million across the remainder of 2026 and 2027.

The coming months will see a significant increase in operational activity at Ntorya, with work commencing at NT-1, testing and first production from NT-2, completion of the pipeline and the planned drilling of NT-3. Importantly, the provisional 2027 programme provides a clear pathway for further early drilling at the NT-E and NT-W locations as we move beyond first production and into the broader development of the Ntorya field.

We remain focused on maintaining the current momentum and delivering first gas in December."

 

 

For further information:

 


Aminex PLC

+44 203 355 9909

Charles Santos, Executive Chairman




Knights Media & Public Relations

aminex@knightsmpr.com

Sabina Zawadzki




Davy

+353 1 679 6363

Brian Garrahy

 


Shard Capital

+44 20 7186 9952

Damon Heath




Axis Capital Markets

+44 203 026 0320

Richard Hutchison




 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 

Companies

Aminex (CDI) (AEX)
UK 100