Ntorya Operations Update

AI SummaryClose X

Aminex plc has provided an update on the Ntorya development in Tanzania, confirming that civil works commenced on schedule at the end of January 2026. Engineering and surveying contracts for the Ntorya-2 well hook-up have been awarded, with the principal contract expected soon, and a shortlist of drilling rig contractors for the Chikumbi-1 well and Ntorya-1 workover has been finalised. Additionally, line pipe for the pipeline from Ntorya to Madimba has arrived on site. Aminex holds a 25% non-operated interest and is carried through the work program up to a gross capital expenditure of $140 million, which is expected to cover costs until commercial gas production begins.