Ntorya Operations Update

AI SummaryClose X

Aminex PLC announced that the Tanzania Petroleum Development Corporation (TPDC) provided an update on the pipeline from the Ntorya gas field to the Madimba gas processing plant, stating that contractors have begun procuring necessary equipment, with construction equipment mobilization slated for September 2025. Groundwork and pipelaying are expected to commence in January 2026 and be completed by July 2026. The Petroleum Upstream Regulatory Authority (PURA) has approved the tender strategy for contracting a rig to drill the Chikumbi-1 well and perform work on the Ntorya-1 well. Aminex has a 25% non-operated interest and is carried throughout the work program to a maximum gross capital expenditure of $140 million, with Aminex's net share being $35 million.