Active Energy Group PLC has achieved early energisation at its Ghummud site, significantly ahead of schedule, with modular digital infrastructure deployment commencing. This milestone, along with the expected completion of the Kazna transaction by the end of April, will provide approximately 5.5 MVA of capacity. Together, Ghummud and Kazna are projected to generate around US$2.6 million in annual revenue and US$1.2 million in annual free cash flow, supporting the company's strategy of acquiring existing grid connections for faster, more capital-efficient revenue generation and its target of 100MW rollout. The company is also pursuing two additional grid connection opportunities.