Richmond Hill has completed four diamond drill holes totalling approximately 780 metres of a planned ~1,400-metre Sakoose programme (about 56% complete) with a fifth hole underway; hole 4 was extended from ~220m to ~260m (+40m) after visual core inspection and geological review, the rig has moved to the next site where the deeper of two planned holes (originally hole six) is being drilled and the shallower hole has been deferred with remaining metres to be reallocated, and no assay results are yet available while geological logging and sampling continue.