Completion of Feasibility Study on Soweto Cluster Tailings Storage Facilities

Summary by AI BETAClose X

Pan African Resources has completed a feasibility study for its Soweto Cluster Tailings Storage Facilities, identifying a preferred option to add a 600,000 tonnes per month expansion circuit to the existing Mogale Tailings Retreatment complex. This integrated circuit, with an anticipated construction period of 24 months and a capital cost of approximately US$160 million (ZAR2.8 billion), is expected to yield 30-35,000 ounces of gold annually for about 15 years at an all-in-sustaining-cost of US$1,000-US$1,200 per ounce. The project demonstrates strong financial returns, with a post-tax NPV of US$129.7 million and an IRR of 29.4% at a US$2,800/oz gold price. Concurrently, a short-term expansion at the MTR complex will increase gold production from 50,000oz/yr to 60,000oz/yr by December 2025. The company anticipates being fully de-geared by February 2026, providing financial flexibility for project funding.