Update on Val Vedello Exploration Permit Application

AI SummaryClose X

Reveille's Italian subsidiary FEI received a formal request from Italy's MASE on 26 November 2026 for supplementary technical and environmental information following its July 2026 EIA submission and a public consultation that closed 2 November 2026; MASE requested data on geology, geotechnics, hydrogeology, radiological protection, epidemiology, biodiversity, monitoring, infrastructure and safety. FEI has begun collecting data and preparing responses and intends to progress a three-year exploration programme of 156 diamond core drill holes totalling approximately 21,000 metres from about 10.5 kilometres of existing underground galleries to define a Mineral Resource Estimate under international standards, which may affect permit timing.