Wet Concentrator Plant A project update and 2025 guidance update

Summary by AI BETAClose X

Kenmare Resources plc has provided an update on its Wet Concentrator Plant A upgrade project, now expecting it to achieve nameplate capacity in Q1 2026 due to slimes management issues, though the capital cost estimate remains at $341 million. Consequently, 2025 ilmenite production is guided to be not less than 830,000 tonnes, with shipments expected to be approximately 980,000 tonnes of finished products. Total cash operating cost guidance is maintained between $228 million and $252 million.