Wet Concentrator Plant A project update and 2025 guidance update

Summary by AI BETAClose X

Kenmare Resources plc has updated its 2025 production guidance downwards to 870,000 to 905,000 tonnes of ilmenite, plus co-products, due to commissioning delays with its Wet Concentrator Plant A upgrade project, which involved new dredges and a feed preparation module. Despite these challenges, the company expects to meet its shipment commitments for 2025 and 2026 due to existing inventory and anticipates shipping over one million tonnes of finished products this year. The total capital cost for the WCP A upgrade remains $341 million, with approximately 85% expected to be incurred by year-end, and cash operating costs are now projected at $235 to $245 per tonne of finished product.