Falcon Oil & Gas Ltd. - Beetaloo drilling and planned stimulation update

Summary by AI BETAClose X

Falcon Oil & Gas Ltd provided an update on its Beetaloo Sub-basin drilling campaign, where the first two wells of the 2025 program have been drilled and cased, each featuring a 3,000m horizontal section. A 60-stage stimulation is planned for one of these wells, with a 30-day flow test expected in early 2026. Stimulation of the remaining three wells is anticipated in Q2 2026. All wells in the Shenandoah South Pilot Project are expected to deliver the contracted 40 MMcf/d volume under the Gas Sales Agreement. Construction has commenced on the A$140 million Sturt Plateau Compression Facility, and work has begun on the A$70 million, 37-kilometre Sturt Plateau Pipeline. Falcon Australia opted to reduce its participating interest in the three wells drilled in 2025 to 0%.