Operational update

Summary by AI BETAClose X

Amaroq Ltd. announced continued operational improvements at its Nalunaq gold mine, with gold production reaching approximately 5000 oz by October 7, 2025, aligning with revised full-year guidance. A planned four-week shutdown for commissioning activities is expected to commence in the third week of October to fully automate the gravity circuit and complete major civil works. The company remains on track to achieve a nameplate throughput of 300 t/d by year-end 2025. The 4,804 m drilling program at Nanoq has been completed, with initial assay results expected during Q4 2025. A mineral resource update is scheduled for Q1 2026.