Operations Update

 

Silvermere, the independent oil and gas company, focusing principally on exploration, appraisal and production opportunities in the US, is pleased to announce further progress with the tie-in of the I-1 well in its Mustang Island 818-L Field. This is based on information provided by the Operator, Dominion Production Company LLC ("Dominion").

 

The jacket, being the lower section or "legs" of the offshore platform, was set in position on 14 July and pile-driving to secure it to the sea floor commenced on 15 July. As of last night, sea and weather conditions remain satisfactory.

 

Further updates will be provided as the work progresses.

 

 

 

--ENDS--

 

For further information please contact:

 

Silvermere Energy plc

Andy Morrison, Chief Executive

 

 

+44 (0)7980 878 561

Merchant Securities Limited (Nominated Adviser and Broker)

Lindsay Mair/Virginia Bull/Catherine Miles

 

 

+ 44(0)20 7628 2200

Rivington Street Corporate Finance Limited

Jon Levinson

 

+44 (0)20 7562 3357

Bishopsgate Communications

Nick Rome/ Anna Michniewicz/ Ivana Petkova                                                 

+44(0)20 7562 3350

 

About Silvermere Energy PLC

 

The Company acquired its interest in the Mustang Asset on 30 August 2011.  This comprises a 33.33 per cent. working interest and 20.83 per cent. net entitlement interest in the Mustang Licence Area, an area within the southern half of the north west quarter and northern half of the south west quarter of the Block 818-L field as defined in State of Texas Oil and Gas Lease numbers 108873 and 108874. The Mustang Island 818-L field, located in Kleberg County waters of the Gulf of Mexico, is a field re-habilitation project targeting bypassed or only partially produced gas-condensate.

 

Early in 2011 the Hercules Offshore 205 jack-up rig was contracted to re-enter the I-1 Well on the Mustang Licence Area which was considered to be the most likely of the historic well sites to provide 14 optimum re-entry conditions. The I-1Well re-entry and side-tracking operation was completed in March 2011 leaving it ready to complete in sand horizons I-1 to I-6. Production and flow testing was carried out during June 2011. The well re-entry programme was led by Dominion as the operator. Gas and oil produced from the I-1Well is proposed to be connected to pipeline infrastructure and tied in via a subsea assembly, constructed for the purpose and then transported to the Six Pigs gas facility.

 

Silvermere's strategy is to acquire a portfolio of US oil and gas licence interests onshore and in shallow offshore waters, characterised by relatively low risk and low cost with the potential for near term production.

 

Silvermere is quoted on the AIM Market of the London Stock Exchange plc (AIM: SLME) with its offices inLondon.


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLLFSADFIRLIF

Companies

Tern (TERN)
UK 100