Songa Offshore SE : Songa Equinox update

Songa Offshore SE : Songa Equinox update

Songa Equinox went on sea trial as planned on 19 March 2015.

Prior to sea trial departure, the inclination test indicated a heavier than expected Light Unit Weight. This will mandate the installation of sponsons and blisters as per those already installed on Songa Encourage and Songa Enabler. The remedial work will be done in Korea by DSME at the yard's cost.

This installation work will impact the delivery time by an estimated up to four weeks using cofferdams.

In close cooperation with our client Statoil, this additional time at the DSME yard will allow to carry out some of the work that was planned to take place in Norway on 3rd party equipment.

Overall, the mobilization and operational readiness are not expected to be materially impacted.

Limassol, Cyprus
24 March 2015

 

For further information, please contact:
Bjørnar Iversen, CEO (+357 996 49 152)

 
This information is subject of the disclosure requirements acc. to §5-12 vphl (Norwegian Securities Trading Act)



This announcement is distributed by NASDAQ OMX Corporate Solutions on behalf of NASDAQ OMX Corporate Solutions clients.
The issuer of this announcement warrants that they are solely responsible for the content, accuracy and originality of the information contained therein.
Source: Songa Offshore SE via Globenewswire

HUG#1905707
UK 100

Latest directors dealings