Czaslaw-1 Stimulation and Test

RNS Number : 7577C
San Leon Energy PLC
19 April 2013
 



19 April 2013

 

San Leon Energy Plc

("San Leon" or the "Company")

 

Czasław-1 Stimulation and Test

 

San Leon Energy is pleased to announce that its planned stimulation and test of the Czasław-1 well on the Company's Nowa Sol Concession in the Permian Basin of Poland will begin on April 22, 2013 with the mobilisation of coiled tubing, nitrogen lift equipment, and surface test equipment from Vechta, Germany. Recent measurements of the well have shown that the well is building pressure.  After taking samples of the fluid in the wellbore the Company has recovered natural gas (including C1-C8) and light oil.  Schlumberger has been contracted to complete this phase of the project.  The Company estimates the following timeline:

 

·      25 April 2013 - acid wash and clean out of the well

·      26-30 April 2013 - acid squeeze into the Main Dolomite reservoir; after soaking lift fluids in the well bore using nitrogen, followed by 3 day flow test up to 400 bbls of oil

·      1 May 2013 - shut-in the well for 5 day build-up with downhole gauges

·      6 May 2013 - decision on a long term test and oil production, based upon results of the acid stimulation and test

 

The Czasław SL-1 well reached a total depth of 1,558 meters Measured Depth (1,229 meters TVD).  The well penetrated 43 meters of the targeted Permian Main Dolomite reservoir.  Petrophysical analysis shows moderate fracturing of the Main Dolomite within an estimated 29 meters of naturally fractured reservoir. Live oil shows were present on 90% of the core plug and detailed petrophysical and core analysis indicates moveable light oil in the Main Dolomite reservoir.  The entire Main Dolomite interval shows high fluorescence suggesting both moveable and residual oil.  Integrated petrophysical and rock-mechanical analyses suggest the well is a good candidate for artificial stimulation to enhance the natural fractures in the reservoir.  There were no indications of water encountered during drilling. The well is the first well on the Czasław structure, with room for additional vertical and/or horizontal wells.  Several similar structures have been identified in the Company's Nowa Sol 3D seismic survey which covers less than 15% of the Nowa Sol Concession area.

 

Executive Chairman, Oisin Fanning commented:

"The recent recovery of hydrocarbons and build-up of pressure in the Czasław-1 well is very exciting. We have been studying the Main Dolomite extensively over the past months with experts both in Europe and North America.  We are now ready to stimulate and test the well and with success immediately move to production.  There is a huge amount of oil in place in the Main Dolomite and we are committed to unlocking both the conventional and unconventional potential of the petroleum system."

 

 

For further information contact:

 

San Leon Energy Plc

Tel: +353 1291 6292

Oisin Fanning, Executive Chairman


John Buggenhagen, Exploration Director




Macquarie Capital (Europe) Limited

Tel: +44 (0) 20 3037 2000

John Dwyer




Fox Davies Capital

Tel: +44 (0) 20 3463 5000

Daniel Fox-Davies


Richard Hail




FirstEnergy Capital LLP

Tel: +44 (0) 20 7448 0200

Hugh R. Sanderson


David van Erp




Westhouse Securities (Nominated Advisor)

Tel: +44 (0) 20 7601 6100

Richard Johnson


Antonio Bossi




College Hill Associates

Tel: +44 (0) 20 7457 2020

David Simonson


Rupert Trefgarne


Alexandra Roper


 

www.sanleonenergy.com

 

Qualified person

 

John Buggenhagen, who has reviewed this update, has over 15 years experience in the oil & gas industry. He has a Ph.D. and M.Sc. in Geophysics from the University of Wyoming and a B.Sc. in Geophysics from the University of Arizona. He is currently the Director of Exploration for the San Leon Energy Group and based in San Leon's Warsaw office in Poland.

 


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCEAKLNFAPDEEF
UK 100

Latest directors dealings