Drilling Update: General

Roc Oil Company Limited 17 November 2005 17 November 2005 ROC OIL COMPANY LIMITED ('ROC') STOCK EXCHANGE RELEASE ACTIVITY UPDATE: GENERAL KEY POINTS • Four plus four month drilling rig contract underway, offshore Western Australia. • Aggressive, company-wide, exploration and appraisal drilling programme: up to 7 wells in the next 4 1/2 months. • Pipeline installation, a key element in the Cliff Head Oil Field Development Project, successfully completed. • Pioneering 2D and 3D seismic surveys onshore Angola successfully completed. 1. Offshore Western Australia: Eight month drilling rig contract underway In late October 2005, ROC commenced a 4 plus 4 month drilling contract with Ensco Australia Pty Ltd when it received the jack-up drilling rig, Ensco 67. Following the drilling of the first well under this contract, Flying Foam-1, in the northern part of the offshore Perth Basin, the rig is relocating to the Cliff Head Oil Field where it is expected to arrive in the next 3 to 6 days. The Ensco 67 will play a key role in the development of the Cliff Head Oil Field. During the next 4 months the rig will drill and complete 6 production wells and 2 water injection wells and also install the production jacket and topside facilities. After the Ensco 67's work at Cliff Head has been completed the rig will drill 3 to 5 exploration wells in the area around the Cliff Head Oil Field. Importantly, the rig contract is structured so that ROC has an option to extend it for a second 4 month tranche beyond the initial 4 month firm contract period. Therefore, as the Ensco 67 completes its presently designated work programme at Cliff Head, ROC will have the right, but not the obligation, to use the rig on other ROC-operated wells offshore Western Australia, including any farmin opportunities which may arise. 2. Company-wide drilling programme Attachment 1* is the latest update of ROC's company-wide drilling programme for the period mid-November 2005 to March 2006: up to 7 exploration and appraisal wells in the next 4 1/2 months. The main change since the previous programme was distributed is: • Wells tentatively scheduled for deep water Equatorial Guinea and onshore New Zealand, previously highlighted as being particularly susceptible to delay due to the tight rig market, will not be drilled prior to April 2006 because of the lack of suitable rigs. 3. Cliff Head Oil Field: Pipeline activities completed The pipelines, power cable and umbilical (collectively the 'pipeline') construction and installation elements of the Cliff Head Oil Field Development were successfully completed on 15 November. In contrast to the traditional approach to such projects, which would normally involve the appointment of a single, over-arching pipeline contractor, all components of the pipeline operation were directly contracted by ROC, as Operator of the Cliff Head Joint Venture. In order to expedite this contract strategy ROC structured a special purpose third party pipeline management company staffed with a team of highly experienced individuals, recruited from the pipeline industry, headed by Mr Peter Cox, reporting directly to ROC's Cliff Head Project Manager, Mr Duncan Mitchell. As a consequence of this arrangement, ROC was responsible for all phases of pipeline construction and installation, including the direct purchase of materials, the leasing and manning contract services of the pipelay barge spread and accommodation vessel, and the management and supervision of the onshore-offshore pipeline installation, including the under-beach horizontal drilling which was designed to minimise the environmental impact of the project. The pipeline project was completed a few weeks later than originally scheduled, mainly due to weather downtime with the pipelay vessel. Fortunately, this delay, which has not affected the overall Cliff Head project schedule, still allowed the pipeline phase of the project to be completed just as the crayfishing season started offshore Dongara. 4. Angola: 2D and 3D seismic surveys completed Roc Oil (Cabinda) Company, a wholly owned subsidiary of ROC, Operator of the Cabinda South Block, onshore Angola, is pleased to advise that it has completed its 2005 seismic programme. Over a five month period, 162 sq km 3D seismic and 505 km 2D seismic were acquired. The surveys represent the first substantial exploration activity to take place onshore Angola for more than 30 years. The 3D survey was a 'first' for onshore Angola. The seismic was acquired by the Geophysical Institute of Israel while matters related to explosive ordnance disposal were undertaken by Demining Enterprises International (Pty) Ltd. At the height of survey activity almost 300 people were employed, the vast majority of whom were locals. Preliminary results of the seismic processing confirm that data quality is generally good to excellent and there is an abundance of structuring, although it is too early to tell how many of the structures represent valid closures worthy of drilling. The Cabinda South Joint Venture plans to undertake another substantial seismic survey next year ahead of a multi-well exploration drilling programme. This drilling programme is currently targeted to start in late 2006, subject to onset of the year-end rainy season, rig availability and the results of the seismic interpretation which has just begun. CEO's Comments Commenting on the various activities referred to above, ROC's CEO, Dr John Doran, stated that 'ROC's activity level remains very high and important individual operational milestones are being achieved. It is particularly pleasing to have safely completed both the seismic programmes onshore Angola and the pipeline operations offshore Western Australia. While ROC's future drilling programme will - like every other drilling programme in the industry - remain sensitive to the tight rig market which currently prevails, the signing of a 4 month plus 4 month optional drilling contract with more rig capacity than is presently required, strengthens ROC's strategic position with regard to drilling opportunities offshore Western Australia.' *Attachment 1 is avaiable with the copy of this release on ROC's website. (http://www.rocoil.com.au/Pages/ASX_Releases/2005_Releases/November-2005.html) Michelle Manook For further information please contact: General Manager - Corporate Affairs Dr John Doran on Tel: +61-2-8356-2000 Fax: +61-2-9380-2635 Email: jdoran@rocoil.com.au Or visit ROC's website: www.rocoil.com.au Dr Kevin Hird General Manager Business Development Tel: +44 (0)207 586 7935 Fax: +44 (0)207 722 3919 Email: khird@rocoil.com.au Nick Lambert Bell Pottinger Corporate & Financial Tel: +44 (0)207 861 3232 This information is provided by RNS The company news service from the London Stock Exchange
UK 100

Latest directors dealings