Second Quarter Trading Update

RNS Number : 5105X
OPG Power Ventures plc
20 November 2014
 



20 November 2014

 

OPG Power Ventures plc

("OPG", the "Group" or the "Company")

 

Trading update for the three months ended 30 September 2014

 

OPG Power Ventures plc, the developer and operator of group captive power generation plants, announces the following trading update for the three months ended 30 September 2014 ("Q2 FY15").

 

Highlights

·   Plant Load Factor (PLF) of 82% in Q2 FY15 and 88% in H1 FY15 following planned shutdowns at Chennai I and Chennai II of 27 days and 7 days respectively

·   Average tariff of Rs5.58 realised per kWh

·   New agreement for sale of 255 MW to TANGEDCO from Chennai at Rs5.50 per kWh until Sep 2015

·   480 MW Projects - construction activities being completed, equipment tests ongoing ahead of commissioning expected to start in December 2014

·   Gujarat transmission lines - construction continues

·   Imported coal booked for Chennai until March 2015 and first deliveries received for Gujarat

 

Operations Summary

 

Parameter

Quarter ended

30 Sep 14

Quarter ended

30 Jun 14

Quarter ended

30 Sep 13

Half year ended

30 Sep 14

Half year ended

30 Sep 13

Year ended    

31 Mar 14








 

Generation (million units)







Chennai I

115

148

164

263

332

646

Chennai II

158

169

172

327

334

668

Chennai III

152

160

143

312

177

527

Total (million units)

425

477

479

902

843

1,841








PLF (%)







Chennai I

67

88

97

78

98

96

Chennai II

93

100

101

97

99

99

Chennai III

86

92

81

89

78

92

Average (%)

82

93

93

88

93

96








Tariff (Rs/kWh)

5.58

5.56

5.52

5.57

5.56

5.55

 

Power generation in Q2 FY15 was 9% lower than the immediately preceding quarter at 425 million units (Q2 FY14: 477 million units) on account of planned shutdowns taken during the period.   Energy generation during the first half as a whole was nevertheless 7% higher than in the comparable period in the prior year at 902 million units (H1 FY14: 843 million units).  Following its first major planned shutdown in 42 months, Chennai I resumed service at a PLF of over 92% and 95% in August and September respectively.

 

480 MW new capacity - construction being completed and final pre-commissioning trials underway

 

Construction at both 300 MW Gujarat and 180 MW Chennai IV project sites is being completed now and pre-commissioning equipment trials are underway.  This should pave the way for commissioning trials to start in December which in turn should allow the Company to be ready to commence commercial operations in the following quarter once transmission lines are made available as planned in Gujarat and utilising existing transmission lines in Chennai.

 

Gujarat Energy Transmission Company Limited ("GETCO") continues with the construction of the new multi circuit transmission line for large scale evacuation of power from our plant as well as constructing a lower capacity double circuit transmission line.  We anticipate transmission lines in Gujarat to be ready for us to dispatch power in the next quarter.

 

The Gujarat plant is expected to use a blend of domestic and imported coal. Until domestic linkage coal is made available, we are procuring coal under short term agreements with the Group's existing suppliers of imported coal.  Our first such shipment recently arrived at the Gujarat site.

 

Outlook

 

Our projects are on track to commission shortly and overall trading in the current year remains in line with expectations.

 

For further information, please visit www.opgpower.com or contact:

 

OPG Power Ventures PLC

+91 (0) 44 429 11 211

Arvind Gupta

 

V Narayan Swami

Ajay Paliwal

 

 

 

Cenkos Securities (Nominated Adviser & Broker)

 

Stephen Keys / Mark Connelly / Callum Davidson

+44 (0) 20 7397 8900

 

 

Tavistock Communications

 

Simon Hudson / James Collins

+44 (0) 20 7920 3150

 

About OPG

OPG is operating and developing power plants in India under the group captive model with 270 MW in operation and a further 480 MW under development.  In the year ended 31 March 2014, the Company generated revenues of £99 million, EBITDA of £31 million and earnings per share of 4.1 pence.

 

-ends-


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
TSTZMMMMZLMGDZZ
UK 100

Latest directors dealings