Nelson Work Completed

Enterprise Oil PLC 13 August 2001 Nelson Work Completed Enterprise Oil has announced the completion of remedial work on the gas compressor on its Nelson platform in the UK Central North Sea. The facility had been producing at reduced rates of around 25,000 barrels of oil per day while the work was undertaken onshore by the original equipment manufacturer. The remedial work was completed on schedule, and following the successful return and re-installation of the compressor onto the platform, the field has returned to production levels of around 70,000 bopd. Enterprise has operated the Nelson field since first oil in 1994. It was discovered in 1988 and has produced over 300 million barrels of oil. Ends. For further information please contact: Patrick d'Ancona, Head of Public Relations 020 7925 4160 Sucharita Sethi, Senior External Affairs Advisor 020 7925 4160