Costain wins £85m M53 contrac

RNS Number : 5000M
Costain Group PLC
30 January 2009
 





COSTAIN GROUP PLC

('Costain' or 'the Group')


Costain wins contract for M53 Bidston Moss Viaduct Strengthening


The Highways Agency has awarded Costain a design and construction contract to strengthen the M53 Bidston Moss Viaduct and restore the network to full capacity loading requirements. The project will be managed by the Highways Agency with a total value of the project of £85m.


Bidston Moss Viaduct is a 730 metre long box girder bridge which carries the M53 over the A554 roundabout and the Birkenhead to New Brighton railway, and is jointly owned by the Highways Agency, Wirral Council and Merseytravel, owners and operators of the Mersey Tunnels.  The scheme will involve major strengthening work to the existing viaduct at Junction 1 of the M53. 

The Viaduct was opened in 1970 and is the main route into the Kingsway Tunnel under the River Mersey. It is used by over 50,000 vehicles daily including 3,000 heavy goods vehicles.

Design work will start this month and last for 15 months, while construction will start in summer 2010 and take around 20 months to complete.


Commenting on the contract award, Andrew Wyllie, Chief Executive of Costain Group, said:


'This contract award further underlines our position as one of the leaders in the construction and maintenance of highways in the UK.'



30 January 2009



ENQUIRIES:




Costain 

Tel: 01628 842444

Graham Read, Communications Director




College Hill

Tel: 020 7457 2020

Mark Garraway


Adam Aljewicz






This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
CNTDGGZMNLMGLZM
UK 100