Quarterly Activities Report and Appendix 5B

Celsius Resources Limited
31 October 2023
 

31 OCTOber 2023

CELSIUS RESOURCES LIMITED

QUARTERLY ACTIVITIES REPORT FOR QUARTER ENDED 30 SEPTEMBER 2023

 

mcb project obtains dmpf approval

HIGHLIGHTS

· Approval of MCB Project's Declaration of Mining Project Feasibility

· Issuance of Exploration Permit for the Botilao Copper-Gold Prospect

· Closing cash as at 30 September 2023 of A$3.7 million

Celsius Resources Limited ("Celsius" or the "Company") (ASX, AIM: CLA) is pleased to provide the following summary of the Company's activities for the quarter ended 30 September 2023.

 

 

Projects

Maalinao-Caigutan-Biyog Copper-Gold Project ("MCB Project"),
Philippines (40%)

Makilala Mining Company Inc. ("MMCI"), Celsius' Philippine subsidiary, has progressed its permitting requirements and is preparing for the pre-development phase of the MCB Project in the Cordillera Administrative region, approximately 320km north of Manila.

 

The MCB Project's Declaration of Mining Project Feasibility (DMPF) was approved on 28 September 2023[1]. This enabled the Company to move forward with obtaining a Mineral Production Sharing Agreement (MPSA) prior to the end of the year with the Philippine National Government, that would allow the development and operation of the MCB Project.

 

Pertinent requirements have been submitted to the Philippine Mines and Geosciences Bureau for evaluation and approval, including a Three-Year Development/Utilisation Work Program which details the phased approach for the development, construction and operation of the project.

 

BOTILAO COPPER-GOLD PROSPECT (40%)

Another tenement was recently awarded under the MMCI portfolio of assets, the Botilao Copper-Gold Prospect, was issued an exploration permit on 7 August 2023[2]. The tenement is located in the Cordillera Administrative Region, southwest of the MCB Project.

 

Results of the historical exploration work in the area conducted by Lepanto Consolidated Mining, Inc. in the '70s along with the current geological understanding of the MCB Deposit will provide the initial working model for the Botilao Prospect work program.

 

Exploration works for the initial two-year permit aims to define the extent and distribution of the observed mineralisation along Botilao Creek, which will consist of regional to semi-detailed geochemical sampling and mapping to generate future targets for possible geophysical surveys and eventual diamond drilling activities.

 

Along with geochemical sampling, mapping of different rock types or lithologies in the area will be conducted to characterise and delineate mineralised or altered zones. Detailed mapping will focus on identified mineralised outcrops to ensure proper understanding of the classification and controls of mineralisation.

 

The Exploration Work Program will be complemented by an Environmental Work Program which outlines the protection and enhancement activities during the exploration period, as well as a Community Development Program consisting of socio-economic projects which will be identified in consultation with the host community.

 

The Botilao prospect is envisaged to bring additional value to Celsius' portfolio and complement the MCB Project once developed.

 

Opuwo Cobalt Project, Namibia (95%)

During the quarter, metallurgical test work continued to optimise floatation, roasting and leaching conditions for the Opuwo project.  Final results and reports are expected in the next quarter, these results along with additional mine planning work that is being conducted in the Philippines will be used as a basis to evaluate the viability of the project and what additional studies may required with the objective to produce a revised Scoping Study for the Opuwo project during 2024.

 

The Company continued to engage with the Government of Namibia to advance the renewal of its mineral rights (EPL 4346) which covers the full extent of the Opuwo project. From recent engagement with the Ministry of Mines and Energy, it became evident that all technical assessments for the renewal have been completed and finalisation of renewal of EPL 4346 is a now an act of formalisation, which is anticipated to be completed in the next quarter.

 

SAGAY Copper-Gold Project, Philippines (100%)

Celsius Resources' Philippine subsidiary, Tambuli Mining Company, Inc., on the island of Negros, has ramped up activities to complete the remaining commitments under its Exploration, Environmental, and Community Development Programs.

 

Activities conducted from July to September 2023 focused on the shallow high-grade copper, or the Secondary Supergene Chalcocite Enrichment zone (900SG Domain). This is a logical approach based on the results of the desktop studies and the Maiden Mineral Resource Estimate[3].

 

A drilling program was concluded to supplement the data gaps and to increase the resource estimation confidence of the shallow high-grade zone. Eleven diamond drill holes were completed with a total of 824.70 meterage drilled while one (1) hole was abandoned due to the intersection of the shallow water table.

 

Table 1. Drilling Summary

Hole ID

Date Started

Date Finished

Coordinates

Elevation (m)

Azimuth

(o)

Dip

(o)

Depth (m)

Core Sizes

PQ

(m)

HQ

(m)

NQ

(m)

SGY-039

08/07/2023

08/09/2023

                542853mE,

1195396mN

123

135

-60

60

0.00 to 60.00 (EOH)

-

-

SGY-040

08/10/2023

08/13/2023

                542736mE,

                1195313mN

118

135

-60

80

0.00 to 80.00 (EOH)

-

-

SGY-041

08/14/2023

08/14/2023

(abandoned)

                542845mE,

                1195305mN

117

135

-60

14.2

0.00 to 14.20 (EOH)

-

-

SGY-042

08/15/2023

08/15/2023

                542722mE,

                1195396mN

115

135

-60

60

0.00 to 60.00 (EOH)

-

-

SGY-043

08/15/2023

08/18/2023

                542836mE,

                1195244mN

129

135

-60

80

0.00 to 80.00 (EOH)

-

-

SGY-044

08/19/2023

08/21/2023

                542664mE,

                1195363mN

124

135

-60

80

0.00 to 80.00 (EOH)

-

-

SGY-045

08/19/2023

08/22/2023

                542682mE,

                1195242mN

150

135

-60

80

0.00 to 80.00 (EOH)

-

-

SGY-046

08/23/2023

08/25/2023

                542610mE,

                1195259mN

137

135

-60

80

0.00 to 80.00 (EOH)

-

-

SGY-047

08/23/2023

08/26/2023

                542603mE,

                1195193mN

126

135

-60

60

0.00 to 60.00 (EOH)

-

-

SGY-048

08/26/2023

08/28/2023

                542628mE,

                1195117mN

131

135

-60

60

0.00 to 60.00 (EOH)

-

-

SGY-049

08/27/2023

08/29/2023

                542665mE,

                1195305mN

134

135

-60

90.5

0.00 to 90.50 (EOH)

-

-

SGY-050

08/30/2023

08/31/2023

                542771mE,

                1195206mN

139

135

-60

80

0.00 to 80.00 (EOH)

-

-

 

All drill cores were geotechnically and geologically logged. Geochemical core sampling have also been completed and submitted to a laboratory for analysis. Assay results of the shallow drill holes are intended to upgrade the resource estimation of the shallow copper zone. Collection of samples for further metallurgical test works which is ongoing. This is aimed at providing a thorough process flow for the extraction of copper/copper mineral concentrate by means of gravity separation. Results of the analysis will be the basis for the mine plan, process flow sheet, and financial studies which are critical components of the project's viability.

 

Environmental and Social Studies have been completed that would serve as baseline data for the Environmental Impact Statement for the project which is underway.

 

In parallel, the Company is also preparing the mandatory requirements for the application of Declaration of Mining Project Feasibility (DMPF) to be submitted within the term of the exploration permit.

 

Cullarin West Project, NSW (100%)

The Company is continuing to assess the viability of the opportunity and gauge interest from other possible partners. No development activities were conducted during the quarter.

 

Corporate and Expenditure

 

As announced to ASX on 15th May 2023, Celsius and Silvercorp Metals Inc. ("Silvercorp") entered into a term sheet which outlined the nonbinding key terms upon which, amongst other things, Silvercorp would acquire 100% of the issued capital of Celsius pursuant to a scheme of arrangement ("Scheme"). The term sheet also contemplated an inter-conditional spin-out of the combined Sagay (Philippines) and Opuwo Cobalt (Namibia) projects ("Demerger"). The parties had substantially completed the negotiations with regards to the legally binding agreements for the Scheme and Demerger as contemplated.

 

However, following initial feedback received by Celsius from its shareholders, the Company had sought to advance discussions with Silvercorp regarding a number of key commercial aspects of the transaction.

 

The Company announced on 2nd August 2023 that the exclusivity under the term sheet had expired, and at that time Celsius remained committed to advancing the discussions with Silvercorp with a view to executing binding agreements considering the best interests of Celsius shareholders. Since then, discussions with Silvercorp have not eventuated.

 

Cash Position

 

At the end of the quarter, the Company held approximately A$3.7 million in cash reserves.

 

ASX ADDITIONAL INFORMATION

 

The Company provides the following information pursuant to ASX Listing Rule requirements:

 

·    ASX Listing Rule 5.3.1:

Approximately A$572k was spent on exploration expenditure, with $318k primarily relating to the development of the MCB project.

·    ASX Listing Rule 5.3.2:

The Company confirms that there was no mine production and development activities for the quarter.

·    ASX Listing Rule 5.3.5:

The Company advises that there were A$380k in payments made to related parties of the Company and their associates during the quarter, for Director and consultancy fees[4].

 

Tenement Table: ASX Listing Rule 5.3.3 Mining tenement interests held at the end of the quarter and their location

 

PERMIT
NAME

PERMIT
NUMBER

REGISTERED HOLDER / APPLICANT

PERMIT STATUS

PERMIT EXPIRY

INTEREST / CONTRACTUAL RIGHT

Western Australia

Cullarin West

EL 8996

Cullarin Metals Pty Ltd

Granted

17/08/2026

100%

Namibia


EL 4346*

Gecko Cobalt Holdings

Permit application, pending approval

 

TBA

95%

Philippines

Maalinao-Caigutan-Biyog

EP-003-2006-CAR

Makilala Mining Company Inc.

Granted

Waiting for the MPSA Mining permit to be issued.

40%

Colayo

EXPA-073-CAR

Makilala Mining Company Inc.

Granted

29/09/2025

40%

Panaon

EXPA-000127-VIII

PDEP, Inc.

Complying with further permitting requirements

TBA

100%

Sagay

EP-000003-VI

Tambuli Mining Company Inc.

Granted

10/02/2024

100%

 

*Tenement expired on 7 March 2023 and a permit application is pending approval. The tenement remains active until such time that it is renewed by the Ministry of Mines.

It is the Company's view that all permit obligations have been met during the existing permit tenure, and therefore the permit renewal is expected for a period of 2 years. 

 

The Maalinao-Caigutan-Biyog (MCB) project has gained an automatic extension as all documentation has been submitted to the Philippine National Government for the awarding of a MPSA Mining permit.

 

The mining tenement interests acquired during the quarter and their location:

Nil.

 

Beneficial percentage interests held in farm-in or farm-out agreements at the end of the quarter:

Not applicable.

 

Beneficial percentage interests in farm-in or farm-out agreements acquired or disposed of during the quarter:

Nil.

 

 

This announcement has been authorised by the Board of Directors of Celsius Resources Limited.

 

The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 as it forms part of UK Domestic Law by virtue of the European Union (Withdrawal) Act 2018.

 

For further information contact:

Celsius Resources Limited

 

 

Peter Hume

P: +61 8 9482 0500

E: info@celsiusresources.com.au

W: www.celsiusresources.com

 



 

Multiplier Media

(Australian Media Contact)            


 

Jon Cuthbert

 

 

M: +61 402 075 707

E: jon.cuthbert@multiplier.com.au

 

 

 

Tavistock Communications

(UK Media and Investor Relations)

P: +44 (0) 207 628 3396

Charles Vivian

 

M: 0044 7977297903

E: charles.vivian@tavistock.co.uk

Tara Vivian-Neal

M: 0044 7394408654

E: tara.vivian-neal@tavistock.co.uk



 

Beaumont Cornish Limited

(Nominated Adviser)

Roland Cornish/Andrew Price

 

 

 

P: +44 (0) 207 628 3396

E: corpfin@b-cornish.co.uk

 

SP Angel Corporate Finance LLP (Broker)

P: +44(0) 203 470 0470

 

John Meyer/Ewan Leggat/Harry Davies-Ball

E: contact@spangel.co.uk

 

 


Competent Persons Statement

 

Information in this report relating to Exploration Results and Mineral Resources for the MCB Project and the Sagay Project is based on information compiled, reviewed and assessed by Mr. Steven Olsen, who is a Member of the Australasian Institute of Mining and Metallurgy and the Australian Institute of Geoscientists. Mr. Olsen is a consultant to Celsius Resources Limited and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined by the 2012 Edition of the Australasian Code for reporting of Exploration Results, Mineral Resources and Ore Reserves.  Mr. Olsen consents to the inclusion of the data in the form and context in which it appears.

 

The information in this Report that relates to the estimate of Mineral Resources for the Opuwo Project is based upon, and fairly represents, information and supporting documentation compiled by Mr Kerry Griffin, a Competent Person, who is a Member of the Australian Institute of Geoscientists (AIG). Mr Griffin is a Principal Geology Consultant at Mining Plus Pty Ltd and an independent consultant engaged by Celsius Resources Pty Ltd for this work and has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves" (the JORC Code). Mr Griffin consents to the inclusion in this announcement of matters based on his information in the form and context in which it appears.

 

The Company confirms that it is not aware of any new information or data that materially affects the Mineral Resource for the MCB[5] Project, the Sagay[6] Project or the Opuwo[7] Project. The Company also confirms that all material assumptions and parameters underpinning the Mineral Resource estimate continue to apply and have not materially changed.

 

Forward Looking Statements

 

Some of the statements appearing in this announcement may be in the nature of forward-looking statements. You should be aware that such statements are only predictions and are subject to inherent risks and uncertainties. Those risks and uncertainties include factors and risks specific to the industries in which the Company operates and proposes to operate as well as general economic conditions, prevailing exchange rates and interest rates and conditions in the financial markets, among other things. Actual events or results may differ materially from the events or results expressed or implied in any forward-looking statement.

 

No forward-looking statement is a guarantee or representation as to future performance or any other future matters, which will be influenced by a number of factors and subject to various uncertainties and contingencies, many of which will be outside the Company's control.

 

The Company does not undertake any obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after today's date or to reflect the occurrence of unanticipated events. No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or correctness of the information, opinions or conclusions contained in this announcement. To the maximum extent permitted by law, none of the Company's Directors, employees, advisors, or agents, nor any other person, accepts any liability for any loss arising from the use of the information contained in this announcement. You are cautioned not to place undue reliance on any forward-looking statement. The forward-looking statements in this announcement reflect views held only as at the date of this announcement.

Appendix 5B

Mining exploration entity or oil and gas exploration entity
quarterly cash flow report

http://www.rns-pdf.londonstockexchange.com/rns/7852R_1-2023-10-30.pdf



[1] Refer to ASX announcement dated 28 September 2023

[2] Refer to ASX announcement dated 7 August 2023

[3] Refer to ASX announcement dated 7 November 2022

[4] The average foreign exchange rates for the quarter ended 30 September 2023 to convert the relevant Philippine Peso (1AUD:36.64PHP) and Namibian Dollar (1AUD:12.22NAD) amounts to Australian Dollars are sourced from https://exchangerates.org.uk/

[5] Refer to ASX announcement dated 12 December 2022 for an updated JORC compliant Mineral Resource Estimate.

[6] Refer to ASX announcement dated 7 November 2022 for the Maiden Mineral Resource for Celsius' Sagay Cu-Au Project

[7] Refer to ASX announcement dated 1 July 2021 for the updated Mineral Resource Estimate for the Opuwo Project.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UK 100

Latest directors dealings