Quarterly Report

RNS Number : 2258Q
Berkeley Resources Limited
30 July 2010
 



30 June 2010

BERKELEY RESOURCES LIMITED

Quarterly Activities Report - June 2010

Significant activity toward the initial Feasibility Study for the Salamanca Uranium Project (SUP) took place over the last quarter. Encouraging progress in all project areas has been achieved. Work focused mainly on tank leach metallurgical test work and Reverse Circulation (RC) drilling aimed at upgrading and extending the Mineral Resources announced in the first quarter.

 

The highlights for the quarter:

 

1.  Uranium recoveries up to 94% from metallurgical tank leach tests for composite samples from Sageras, Palacios and Alameda South with a relatively coarse grind and low acid consumption

2.  Recoveries of up to 87% U3O8 in Bottle Roll Leach Test work (BRT) simulating heap leach characteristics in advance of the column leach test work

3.  The Exploitation Plan for the SUP which includes the mining plan, reclamation plan, environmental and radiological study was completed and has been submitted to Berkeley's JV partner ENUSA

4.  Commencement of the RC drilling program at Sageras, Palacios and Alameda South to upgrade resource categories and test for possible extensions. The 8,000m programme was 45% complete by the end of the quarter.  Results to date confirm the resource models and have identified additional potential at Sageras where two holes have discovered a new mineralised zone, and at Alameda where initial chemical assay results are better than expected 

5.  Updated resources for Sageras and Alameda South and new pit optimisations and production schedules will be finalised in the 3rd quarter

6.  The environmental and radiological baseline studies are approximately 60% complete and scheduled to be completed in the 4th quarter 

7.  Approximately five tonnes of "representative" core samples were selected for dispatch to SGS in Perth for column leach test work

8.  A combined RC drilling and diamond drilling programme was planned and submitted to the Mines Department for the Retortillo and Santidad deposits

 

Berkeley Managing Director, Mr. Ian Stalker commented "The quarter has been an extremely productive period as we progressed the Salamanca Uranium Project. The very encouraging tank leach results indicating high recoveries at a coarse grind and low acid consumption add to our knowledge and assist in project design criteria and equipment selection. The infill resource and extension RC drilling programme is nearly 50% complete. The initial results are providing upside to the existing resource models and equally importantly enable upgrading of the Inferred resources at Alameda and Sageras."

 

Enquiries -       Managing Director:       Ian Stalker               Tel:  +34 608 221 497                            

                        RBC Capital Markets:   Martin Eales            Tel: +44 20 7029 7881

Salamanca Uranium Project Feasibility Study

Work towards the initial Feasibility Study is progressing well and is scheduled to be completed by the end of the year.  The Feasibility Study is focussing on a tank leach scenario using the Quercus Plant to produce 2.1mlbs U3O8 per year from the Sageras, Palacios and Alameda South deposit. The aim is to complete the study by the end of the year.  Simultaneously, work is progressing to assess the heap leach options for these deposits and the satellite deposits at Retortillo.

 

1. Drilling Programmes

 

Diamond and RC drilling operated continuously during the quarter for a total of 5,199 metres (Table 1) at Alameda South, Sageras and Palacios.  At the end of the quarter, four RC rigs and one diamond rig were operating.

 

Table 1 - 2nd Quarter Drilling Totals

Deposit

Q2 Drill Holes

Q2 Drill Metres


DDH

RC

TOTAL

DDH

RC

Total

Alameda South

8

21

29

885

2,182

3,067

Palacios North

1

0

1

78

0

78

Sageras

10

20

30

782

1,271

2,053

Total

19

41

60

1,746

3,453

5,199

 

This work addressed several objectives, as detailed below. 

Heap Leach Metallurgical diamond drilling - approximately 1,100 metres of large diameter PQ diamond drilling at Sageras and Alameda was completed in May to generate additional material for metallurgical test work.  These holes were not included in the Mineral Resource Estimates announced in the first quarter but the e-grades correlate well with the resource models and provide further confirmation of the historical drilling data.

 

RC Drilling- approximately 8,000 metres of planned RC drilling commenced in June with the following objectives:

 

·    To upgrade the current resource classifications from Indicated to Measured and from Inferred to Indicated

·      To test for lateral and depth extensions of current resources

·      To test a number of high priority targets identified by surface mapping and ground radiometrics, proximal to the existing resources

·      To complete sterilisation drilling of the area to the north of Sageras where the conceptual waste dump and crushing facility have been located

This programme was approximately 45% complete by the end of the quarter and is scheduled to finish in early August.  All of the RC samples are being sent to ALS Chemex in Vancouver for chemical analysis after preparation at the ALS Chemex laboratory in Seville.  Down hole gamma readings are used to select the anomalous intervals to assay and the calculated e-grades on the completed holes are showing very good correlation with the resource model. 

The initial chemical assay results indicate potential upside to the resource model at Alameda South with some high grade intersections returned in holes ASR-029 (28 - 63m, 35m @ 2,044ppm U3O8), ASR-031 (29 - 55m, 26m @ 3,923ppm U3O8) and ASR-032 (22 - 40m, 18m @ 1,401ppm U3O8).   

At Sageras, two RC holes have identified a new mineralised zone that appears to be open to the north-west.  Hole ZRC-012 intersected very high grade mineralisation from 44m depth over a 3 metre interval grading 7,027ppm U3O8.  This intersection will be followed up by further RC drilling in the next quarter.

A list of notable intersections for the quarter is shown in Table 2.  The diamond drill holes are presented as eU3O8 grades calculated from down hole radiometrics whereas the RC holes are presented as U3O8 chemical assays.

Table 2 - Notable Intersections

Deposit

Hole ID

From

To

Interval

eU3O8



(m)

(m)

(m)

(ppm)

Alameda South

ASD-020

22.7

24.7

1.9

4,814

Alameda South

ASD-021

16.5

21.9

5.4

2,439

Alameda South

ASD-023

37.3

42.6

5.3

3,142



68.3

71.0

2.7

1,934

Alameda South

ASD-024

73.4

83.6

10.2

1,048

Alameda South

ASD-026

30.8

41.7

10.9

1,047



92.8

98.2

5.4

1,239

Alameda South

ASD-027

62.3

67.3

5.0

1,086

Sageras

SGD-020

21.9

24.1

2.2

3,747



25.2

28.8

3.6

4,925

Sageras

SGD-021

47.3

49.0

1.7

2,963







Deposit

Hole ID

From

To

Interval

U3O8



(m)

(m)

(m)

(ppm)

Alameda South

ASR-029

28

63

35

2,044

Alameda South

ASR-031

29

55

26

3,923

Alameda South

ASR-032

22

40

18

1,401

Sageras West

ZMR-012

38

42

4

1,461



44

47

3

7,027



63

71

8

1,716

 

A full table of intersections for the quarter is included in the Appendix.  They have been calculated using a nominal 200ppm lower cut-off and a minimum thickness of at least 1m.  All intersections correlate well with the historical drill hole data in both thickness, location down the hole and grade. 

 

 

 

2. Metallurgical Test Work

During the quarter further representative samples taken from diamond drill core from the Palacios, Sageras and Alameda South deposits were sent to the SGS Metallurgical laboratories in Perth, Australia to continue the ongoing testwork supervised by Orway Mineral Consultants Pty Ltd of Australia.

 

The first phase of the testwork campaign commenced in March 2010 and has been focused on optimising the process conditions for treating the uranium ore lithologies at Sageras, Palacios and Alameda in a tank leach configuration. Phase 1 is scheduled to be completed in the 3rd quarter 2010 with the following testwork in progress:

 

1    Preliminary mineralogy on various ore types

2    Comminution (crushing and grinding)

3    Tank leaching

4    Heap leaching

5    Engineering Data

6    Geotechnical and geochemical testing of the final process residues and

7    Effluent neutralisation

 

The initial results can be found in the Berkeley announcement - "Metallurgical testwork update" released on the 7 June 2010.

 

Mineralogy

 

QEMSCAN mineralogy on composites of the ores from Sageras, Palacios and Alameda has revealed:

1   The Sageras uranium minerals have a finer grain structure (< 20 microns) and are predominantly coffinite with a lesser quantity of uraninite

2   In Palacios, the uranium minerals have a coarse grain structure (20 - 50 micron) with uraninite dominating and lesser quantities of coffinite, often intergrown

3   The Alameda uranium minerals are medium grained in between Sageras and Palacios in grain size and have an almost equal distribution between uraninite and coffinite 

 

On the basis of these results, Palacios has the best leaching characteristics probably because the uraninite is more amenable to leaching than coffinite and coarser grains have more exposed surfaces available to leaching. 

 

Comminution

 

A second batch of metallurgical test work samples consisting of 1,274kg of diamond drill core was sent to SGS in June for detailed comminution test work. This followed a review of the historical comminution flow sheet which showed that a significant uranium concentration can be achieved in a crushing and wet scrubbing process.  This test work commenced during the quarter and is aimed at determining additional comminution data associated with crushing, scrubbing and ball milling. In conjunction with this test work, other physical concentration and gravimetric processes will be examined.  These include:

1   flotation (oxide and sulphide)

2   spirals

3   various gravity processes

 

Agitated Tank Leaching

 

Leach tests are on going on bulk composite samples:

4   Alameda and Palacios continue to yield high leach extractions of uranium of 93 - 94% in batch leaches with modest sulphuric acid consumptions of 18 - 23 kg/tonne of ore

5   The leach extractions for the Sageras composite are typically 87 - 88% at acid consumptions below 10 kg/t

6   All the above results have been achieved at a grind size of P100 ~1.5 mm, at a temperature of 20ºC with very low oxidant requirements of 1 - 2 kg/tonne of commercial pyrolusite

7   The leach-end slurries were amenable to vacuum belt filtration with acceptable treatment rates.  This development will permit the disposal of "dry tailings" resulting in reduced environmental issues

 

Bottle Roll Leach Tests (BRT)

 

During the quarter a parallel static heap leach test work programme commenced to explore the amenability of ore to heap leach. This work started with a suite of intermittent bottle roll tests as a precursor to future column tests, scheduled to start in the 3rd quarter.

The initial bottle roll test have provided an encouraging response for all ores with Sageras at 82%, Palacios at 85% and Alameda at 87% average extractions of uranium.

The consulting group Kappes Cassidy are supervising the heap leach test work after selecting over 5,000kg of diamond drill core from the Alameda South deposit.  This material will be dispatched to SGS Perth in July.  The first one metre column tests are due to start in August with initial results expected in October.

3. Environmental Studies

 

One of the most important components of the Feasibility Study is to establish the Environmental Baseline Study conditions at all of the project sites.  This work is being co-ordinated by Golder Associates with most of the studies commencing during the 1st quarter.  In general, the work is progressing very well with regular monitoring continuing during the quarter and it is on track to be completed by the end of the year. 

 

10 Land-use and landscape. Berkeley retained AIA Consultants to perform the landscape characterisation study. The study commenced in March and the final report is due by the end of July. A soil sampling program was initiated and samples were collected in May. The samples are being analysed at the laboratory of the University of Cantabria for a comprehensive suite of parameters 

11 Climate and Meteorology. A weather station has been installed by INGEMISA in Alameda and it is now working as intended with data being collected and managed by INGEMISA. Historical data will be purchased for nearby weather stations from AEMET (Agencia Estatal de Meterologia). Several locations have also been selected at Aldea del Obispo, Castillejo de Martín Viejo, Ciudad Rodrigo, Fuentes de Oñoro, Gallegos de Argañán, Saelices el Chico and Villar de Argañán. Work is progressing as planned

12 Air Quality. The air quality monitoring program has been developed based on 9 preliminary monitoring points for sedimentable particles (6 in Sageras and Palacios and 3 in Alameda).  Scheduled monitoring of dust particles will commence once the agreements with the landowners have been cleared. Samples will be analysed at INTERLAB for physical/chemical parameters and at EICHROM for radiological parameters

13 Noise. The noise monitoring program has been planned based on a total of 18 monitoring points for baseline noise levels, 12 in Sageras and Palacios and 6 in Alameda. The first monitoring campaign was completed by Berkeley and Golder in April and the next monitoring campaign will be performed in October.

14 Surface Water Quality. The surface monitoring program has been developed based on a total of 7 surface water monitoring points in the area of Sageras and Palacios and 3 surface monitoring points in Alameda. Monitoring is being undertaken by Berkeley under the supervision of Golder Associates and sample analysis is done by AGQ laboratories in Sevilla. The first monitoring campaign was performed in February with ongoing bi-monthly sampling programmes. The results from the first campaign indicate no relevant affection of surface water. In addition, samples of the ENUSA discharge has been taken and sent for analysis

15 Groundwater Quality. The groundwater monitoring programme includes publicly available information from wells and springs in nearby villages. In addition, Golder has established 6 groundwater monitoring points in the area of Sageras and Palacios and 3 groundwater monitoring points in Alameda. Monitoring is being undertaken on a quarterly basis during 2010 with the first campaign completed at the end of March. Sampling and analysis of groundwater is continuing as planned

16 Flora and Fauna.

o The study concerning aquatic flora, fauna and sediments studies has been appointed to IPROMA SL. The scope of works includes surveying and sampling in Alameda, Sageras and Palacios

o The study concerning vegetation and flora studies for the areas of Alameda and Sageras/Palacios has been appointed to the Catedratico Botanical University of Salamanca. A literature study over the areas was performed in March/April and the field campaign started in April (weekly site visits have been planned until July). The final reports are expected in July

o The study concerning fauna (mammals, fish, and reptiles) has been assigned to the University of Salamanca. The study started in May and the final report is expected in August

o The study concerning local birds has been assigned to Estudios Zoologicos Iberia SL. The final report will be delivered by end July. The study includes a special focus on the Black Stork

17 Socio-Economic Baseline. The Socio-Economical Baseline study has been assigned to the Geography Department at the University of Salamanca. The scope of the study includes a compilation of baseline socio-economical data, spatial planning aspects and traffic. The study also includes Phase I of a social acceptance study (identification of relevant target groups and the design of a suitable format of a survey). During May, Golder Associates has discussed the ESIA process and the public consultation processes in relation to the Berkeley Public Relations Strategy in order to co-ordinate the two efforts. A selection process for a potential PR consultant has been initiated.

4. Radiological Studies

The radiation assessment for the Feasibility Study is being conducted by an Australian consulting company, Paulka Radiation & Environment.  All methodology employed in the assessment has been based on international standards recommended by the International Atomic Energy Agency (IAEA) and the International Commission of Radiological Protection (ICRP).  These bodies are recognised by the European Union as the standard for radiation protection.  In addition, recommendations from international best practice guidance material have been incorporated where applicable.

 

The first part of the assessment has been the design and implementation of a baseline monitoring program to characterise the current radiological aspects of the project.  The monitoring programme includes parameters for radionuclides in dust, radon, gamma dose, radionuclides in soils, ground and surface waters and biota.  The baseline monitoring programme commenced in February 2010 and is approximately 50% complete. During the quarter the following monitoring was conducted:

 

1    The second round of surface water sampling was completed and results received for the first and second rounds

2    Water samples were collected from public fountains and results received.

3    Groundwater samples were collected as part of the hydrogeological pumping tests and partial results were received

4    Soil samples from the various landform types were collected in collaboration with the soil and landscape consultants, analytical results are pending

5    Quarterly continuous dust deposition, radon and gamma radiation monitoring commenced

6    Aquatic plants, fish and river sediments were collected by the Flora & Fauna consultants, analytical results are pending

 

Analysis of these results will occur in the 3rd quarter. The remainder of the assessment will involve the identification and quantification of any radiation risks the project may have with regard to workers, the public and the environment. The assessment will recommend design and institutional control mechanisms that will assist in keeping radiation doses optimised to As Low as Reasonably Achievable (ALARA).  The results of the radiation assessment will feed into the Feasibility Study, the Environmental Impact Assessment and applications for authorisations to operate.

 

During the quarter the following radiation assessment tasks were undertaken:

 

1    Collation and analysis of historic radiological data provided by ENUSA. This is now ready for reporting; and

2    Development of draft radiation design criteria for the mining and processing engineering teams for inclusion in the Feasibility Study

 

The majority of the radiation risk assessment has been scheduled for completion during July and August with the final report to be issued in the 4th quarter.

 

5. Water Management

 

The water management programme is progressing well with a significant amount of fieldwork undertaken during the quarter.  The long term groundwater monitoring at Alameda and Sageras is continuing and the short term low rate hydraulic testing is ongoing at Sageras, Palacios and Alameda as well as groundwater tracer tests. Conceptual hydrogeological models have been developed for each deposit:

 

1   Palacios - Permeability (K) of 10-7 m/s will result in 400kl/day groundwater inflows to the pit which are very low and should be easily manageable by pumping with most water being evaporated.

2   Sageras - K between 10-7 and10-6 m/s will result groundwater inflows between 400 to 2,000kl/day.  Flows may be higher in Tertiary covered areas (10-5) where extra flows of up to 300kl per day may be intercepted.  However, surface water can easily be diverted around the open pit.

3   Alameda - K from 10-6 and10-8 m/s resulting in flows from 600 to 2,500 kl/day.

 

These results show that ground water inflows to the open pits should not be excessive and will be easily managed during mining activities. 

 

This on-going work and the results derived are currently being used to complete the water balance and dewatering planning aspects of the water management study.

 

6. Waste Characterisation

 

The waste characterisation programme is a critical part of the Feasibility Study process as all potential waste material types must be identified, classified and characterised as part of the exploitation application process.  This programme is being supervised by Golder Associates and is on schedule although it is dependent on the availability of the residue samples from the metallurgical test work being undertaken at SGS in Perth. These samples are expected to become available in July after which characterisation of the samples can be initiated.

 

During the quarter, a review was conducted of the anticipated waste rock characteristics based on information on the site geology and mine planning. Forty five waste rock samples (Sageras, Palacios and Alameda, five weathering stages and eight lithologies) were selected by Berkeley geologists and reviewed by Golder Associates, before being shipped to SGSCEMI in Vancouver for geochemical characterisation tests including:

 

1    mineralogical analysis by XRD

2    chemical assay

3    acid base accounting (ABA)

4    net acid generation (NAG) testing

5    radiological analysis

 

After completion of the initial testing and review of the analytical results, subsets of these samples were submitted for static leach testing (SPLP) and analysis of NAG leachates. After a review of the leach test results, a smaller subset will be submitted for kinetic testing (HC-tests).

 

In addition, eight residue samples (seven leach products and one water treatment plant residue) and seven feed samples were selected from the tank leach test work program at SGS in Perth for geochemical characterisation. More residue samples will become available by the end of July and these will undergo the geochemical characterisation tests listed above.   After completion of the July testing and review of the analytical results, a subset of these samples will be submitted for analysis of NAG leachates and kinetic testing.

 

7. Mining Studies

A considerable amount of work was undertaken during the quarter following the announcement of the Mineral Estimates at the end of March.  Pit optimisations were completed for various processing and production options and operating costs were further refined following discussions with a number of mining contractors.

 A summary of the mining studies undertaken during the quarter include:

1   The first draft of the Feasibility Study geotechnical report was received from AMC Consultants (UK) which included the configuration of bench batter angles and berm widths.  The new overall pit slope angles range from 45º to 50º resulting in potentially lower strip ratios.

2   AMC Consultants (UK) has completed updated pit optimisations for Palacios, Sageras and Alameda South.  The optimisations used more accurate operating costs after further contact with potential mining contractors, new geotechnical parameters and a U3O8 price of US$60 per lb.

3   Detailed pit designs for all three deposits commenced using the new pit slope and optimised pit shells and will be completed in July.

4   A detailed mining schedule has been developed based on the latest processing plant requirements and using the updated pit optimisation results.

5   A review of the potential waste dump locations was undertaken during the quarter and conceptual designs for the dumps and tailings management facility were completed by Golder Associates. 

6   Trade off studies are underway to look at the cost benefits of an "owner operated fleet" as opposed to using a mining contractor.

7   The January 2008 Scoping Study pit optimsations for Retorillo and Santidad were incorporated into the overall mining schedule.

8. Process Engineering

 

During the quarter, work began on interpreting the test work results and constructing the basic engineering package for more detailed design by Aker Solutions.  The package components include:

1    Basis of Design - testwork interpretation into design data

2    Process Flow diagrams - reflecting the flowsheet details

3    Mass Energy Balance - for the concentrate and metallurgical plants

4    Mechanical Equipment List

5    Motor / Starter List

6    Plant Layout - plot plans

7    Operating Cost Model

The final engineering data will be delivered to Aker Solutions in the 3rd quarter for review and incorporation into the Feasibility Study.  Aker Solutions has also commenced several trade off studies related to the process plant.

 

 

9. Permits and Licensing

 

An application was submitted to the Salamanca Mines Department for infill and extension RC drilling at the Retortillo and Santidad deposits.  The main objective of the drilling campaign is to upgrade the Inferred resources into Indicated and Measured categories.  In addition, 15 diamond drill holes were planned to provide sufficient material for metallurgical heap leach test work.  Table 3 gives a breakdown of the number of holes and metres to be drilled at each deposit.

Table 3 - Retortillo/ Santidad RC Drilling

Deposit

Hole Type

Metres

Holes

Retortillo

RC

8,465

144


DDH

635

9





Santidad

RC

3,445

59


DDH

335

6





Total

RC

11,910

203


DDH

970

15

Work continued during the quarter on the mining exploitation plan which will be submitted to ENUSA in the next quarter.  The Exploitation Plan is the preliminary document that initiates the permitting process and it includes:

1    Mining Plan

2    Reclamation Plan

3    Environmental Study

4    Radiological Study

 

 

 

 

 

 

A full version of this announcement incorporating diagrams can be found of the Company's website www.berkeleyresources.com.au

10. Appendix

 

Palacios Diamond Drill Hole Intersections (e-grades)

Hole ID

Easting

Northing

Elevation

Depth

Azimuth

Dip

From

To

Interval

eU3O8


(m)

(m)

(m)

(m)

(º)

(º)

(m)

(m)

(m)

(ppm)

MDD-016

701093

4500820

633.0

78.45

118

-80

57.1

60.7

3.6

289








68.0

69.1

1.1

2,589

 

 

Sageras Diamond Drill Hole Intersections (e-grades)

 

Hole ID

Easting

Northing

Elevation

Depth

Azimuth

Dip

From

To

Interval

eU3O8


(m)

(m)

(m)

(m)

(º)

(º)

(m)

(m)

(m)

(ppm)

SGD-019

699792

4502947

679.5

87.81



30.6

36.9

6.3

712








40.9

43.0

2.1

1,137








43.6

44.7

1.1

2,207








46.0

49.4

3.4

451








50.5

53.4

3.0

1,290

SGD-020

700372

4502695

645.4

63.20



5.0

6.1

1.1

621








21.9

24.1

2.2

3,747








25.2

28.8

3.6

4,925

SGD-021

700574

4502470

656.1

70.00



31.7

35.2

3.5

463








40.8

42.0

1.2

400








43.5

44.6

1.2

1,595








47.3

49.0

1.7

2,963








56.9

58.0

1.1

2,189

SGD-022

700285

4502755

643.1

139.25

50

-50

12.1

14.4

2.4

1,074

SGD-023

700585

4502088

654.8

42.20



NOT MINERALIZED

SGD-024

700554

4501987

649.8

41.15



NOT MINERALIZED

ZMD-006

699686

4502992

683.6

84.00



NOT MINERALIZED

ZMD-007

699688

4502924

679.8

100.20



53.6

56.7

3.1

355








65.5

66.7

1.2

463

ZMD-008

699655

4503027

684.1

83.70



29.0

33.6

4.6

329








57.2

59.5

2.2

687

ZMD-009

699689

4502852

678.6

70.80



39.3

41.1

1.8

393

 

 

 

 

 



Sageras RC Drill Hole Intersections (chemical assays)

 

Hole ID

Easting

Northing

Elevation

Depth

Azimuth

Dip

From

To

Interval

U3O8


(m)

(m)

(m)

(m)

(º)

(º)

(m)

(m)

(m)

(ppm)

ZMR-010

699668

4502976

680.1

88.00



44

47

3

242








50

51

1

209








53

54

1

435








61

65

4

337

ZMR-012

699580

4503027

674.2

103.00



19

20

1

483








21

23

2

239








25

26

1

321








38

42

4

1,461








44

47

3

7,027








48

49

1

1,633








52

53

1

1,046








61

62

1

1,135








63

71

8

1,716

ZMR-013

699545

4503026

669.6

75.00



31

32

1

441








34

35

1

349








39

44

5

270








46

48

2

255








49

52

3

263








58

60

2

348








64

65

1

253

 

 



Alameda Diamond Drill Hole Intersections (e-grades)

 

 

Hole ID

Easting

Northing

Elevation

Depth

Azimuth

Dip

From

To

Interval

eU3O8


(m)

(m)

(m)

(m)

(º)

(º)

(m)

(m)

(m)

(ppm)

ASD-020

689214

4500696

733.5

70.00

103

-60

0.4

2.9

2.5

927








3.6

4.8

1.2

334








13.7

14.7

1.0

1,257








22.7

24.7

1.9

4,814

ASD-021

689166

4500790

737.8

70.50

103

-60

3.3

4.4

1.1

1,238








9.9

13.3

3.4

2,140








16.5

21.9

5.4

2,439








60.1

61.3

1.2

2,305

ASD-022

689131

4500976

749.0

137.20

103

-72

47.8

49.5

1.8

669








89.8

91.9

2.1

387

ASD-023

689120

4500863

739.3

87.10

103

-60

37.3

42.6

5.3

3,142








47.8

53.4

5.7

724








57.4

58.8

1.4

543








68.3

71.0

2.7

1,934

ASD-024

689052

4500865

738.0

110.08

103

-65

12.2

13.3

1.1

534








19.2

22.3

3.2

586








39.4

40.4

1.0

440








42.4

45.2

2.8

436








50.4

53.3

2.9

1,279








55.0

59.0

4.0

243








62.3

64.1

1.8

393








70.6

72.4

1.8

1,925








73.4

83.6

10.2

1,047

ASD-025

689101

4501036

748.7

147.87

103

-65

104.2

106.2

2.0

606








119.2

120.8

1.6

613








121.0

123.3

2.3

431

ASD-026

688991

4500828

732.8

125.15

103

-65

30.8

41.7

10.9

1,047








43.8

45.7

1.9

1,271








47.6

49.1

1.5

1,102








69.1

71.9

2.8

342








92.8

98.2

5.4

1,239








106.2

114.8

8.6

884

ASD-027

688907

4500797

728.4

136.84

103

-70

62.3

67.3

5.0

1,086








111.8

113.7

1.9

555

 

 

 



Alameda South RC Drill Hole Intersections (chemical assays)

 

Hole ID

Easting

Northing

Elevation

Depth

Azimuth

Dip

From

To

Interval

U3O8


(m)

(m)

(m)

(m)

(º)

(º)

(m)

(m)

(m)

(ppm)

ASR-029

689203

4501188

753.2

99.00

103

-70

22

27

5

585








28

63

35

2,044








67

68

1

233








69

70

1

404








82

83

1

284

ASR-030

689154

4501199

750.9

70.00

103

-70

17

19

2

311








20

26

6

479








29

36

7

618








41

42

1

269








43

45

2

431








46

47

1

257








54

55

1

229








61

62

1

498








68

70

2

533

ASR-031

689191

4501242

751.9

110.00

103

-60

29

55

26

3,923








58

61

3

346








103

106

3

229

ASR-032

689238

4501233

753.8

100.00

103

-60

22

40

18

1,401








41

46

5

478








55

62

7

829

ASR-034

689212

4501340

750.2

120.00

103

-60

52

53

1

347








55

57

2

909








70

71

1

283








73

75

2

270








78

84

6

667








86

87

1

321








99

101

2

203








106

107

1

252








111

112

1

611

 

 

 



11. Supplementary Information

 

The uranium grades reported in this release are annotated with a sub-prefix "e" because they have been reported as uranium equivalent grades derived from down-hole gamma ray logging results and so they should be regarded as approximations only. 

The Berkeley drill holes were logged with a GeoVista total count gamma tool. The gamma tool was calibrated in Adelaide at the Department of Water, Land and Biodiversity Conservation in calibration pits constructed under the supervision of CSIRO. The various calibration factors were calculated by David Wilson BSc MSc MAusIMM from 3D Exploration Ltd based in Perth, Western Australia. 

Drill intersections are calculated using a 200 ppm eU3O8 lower cut-off with a minimum one metre intersection

The Mineral Resources are presented in accordance with the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resource and Ore Reserves" (JORC Code). 

The information in this report that relates to the metallurgical test work results is based on information compiled by Mr Grenvil Dunn, who is a Chemical Engineer and a Member of the South African Institute of Mining and Metallurgy. Mr Dunn is a Technical Consultant with Orway Mineral Consultants who are consultants of Berkeley Resources.  Mr Dunn has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code).

 

 

The information in this report that relates to Exploration Results, Mineral Resources or Ore Reserves is based on information compiled by Mr. Ross Corben, who is a Member of The Australian Institute of Mining and Metallurgy and an employee of Berkeley Resources Limited. Mr. Corben has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the 'Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Mr. Corben consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

 


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLIFLDDIIIVII
UK 100

Latest directors dealings