Hindlip 7.5 MW FlexGen - Construction Completion

Summary by AI BETAClose X

Quantum Data Energy PLC has announced the successful completion of construction and commissioning for its Hindlip 7.5 MW flexible generation power project, which is now grid-energised and ready for commercial operations. The project was delivered below its £5 million capital expenditure budget, with a final spend of approximately £4.63 million, resulting in a saving of £370,000. All construction, commissioning, and grid compliance milestones have been met, and the company expects commercial operations to commence in Q3 2026, marking its second operational flexible generation asset.

Disclaimer*

Quantum Data Energy PLC
01 September 2026
 

Quantum Data Energy PLC

(Incorporated in England and Wales)

(Registration Number: 12886458)

LEI :213800HFVHGJ9YGO9F71

Share code on the LSE: QDE

ISIN: GB00BNG90H86

 

Dated: 1 September 2026

Quantum Data Energy PLC

("Quantum", "QDE" or the "Company")

 

Hindlip 7.5 MW FlexGen Asset Successful Completion of Construction

 

London, UK - Quantum Data Energy PLC (LSE: QDE) is pleased to announce, further to its previous RNS announcement dated 18 March 2026, that its Hindlip 7.5 MW flexible generation power project ("Hindlip"), which is fully funded in partnership with Powertree as previously announced, has successfully completed construction, commissioning, and achieved grid energisation. The project has been delivered below budget, and commercial operations are imminent.

Key highlights and details of the project's completion are provided below.

Hindlip Key Highlights:

QDE is pleased to confirm that all construction and commissioning milestones at Hindlip have now been successfully completed. The high-voltage grid connection was energised on 15 July 2026, G99 grid compliance testing was completed on 22 July 2026, commissioning of all three gensets is complete, and all gensets have since passed their performance testing, together with grid constraint testing. The site is mechanically and electrically complete and ready to enter commercial operations.

The project has been delivered within its approved capex budget of £5 million, with a final forecast spend of approximately £4.63 million, representing a favourable saving of approximately £370,000 due to efficient cost control.

Key progress since the last announcement is as follows:

·   Grid connection energised - The high-voltage connection to National Grid Electricity Distribution ("NGED") was energised on 15 July 2026, notwithstanding the difficult ground conditions encountered by NGED during its cable installation works, which were resolved through the deployment of additional night-time and weekend working;

·   G99 grid compliance achieved - G99 testing was completed on 22 July 2026, confirming the asset's compliance with the Distribution Code and its technical eligibility to export to the grid;

·   Genset commissioning complete - Commissioning of all three Rolls-Royce MTU gensets has been completed and all gensets have passed their performance testing. Grid constraint testing has also been completed, and the site is now ready to enter commercial operations;

·   Civil works complete - All civil engineering works on site are complete;

·   Electrical installation complete - The full on-site electrical installation, including HV and LV cabling, terminations, earthing, and small power and control, is complete, with electrical testing and power-on achieved on 15 July 2026;

·   Gas installation complete - All on-site and off-site gas works are complete, with the gas metering skid commissioned and gas supplied to the gensets;

·   Site infrastructure complete - The control room is in place and fully fitted out, the CCTV system is complete and operational, and the oil storage tanks are installed on site; and

·   Project risk register closed - All items on the project risk register have been closed out, including the NGED cable installation risk, with no open risks remaining at the date of this announcement.

Photographs:

The photos below from the Hindlip site show the completed and commissioned asset:

1.  Completed gensets and radiator cooling packages installed on site

2.  Completed HV switchroom and energised NGED transformer compound

3.  Completed site showing control room, acoustic fencing and gensets

4.  Completed control room and switchroom buildings

Programme and Next Steps:

With energisation, G99 compliance, genset commissioning and performance testing all achieved, the site is ready to enter commercial operations. The remaining step is finalisation of the operations and maintenance ("O&M") arrangements for the site, following which the gensets will be formally signed off and the asset will commence commercial operations, which is expected shortly. The Company expects that Hindlip remains on track for commercial operations during Q3 2026, in line with the timeline set out in the previous announcement. The remaining timeline is as follows:

·   Finalisation of O&M arrangements and formal genset sign-off: early September 2026;

·   Final snagging and handover: September 2026; and

·   Commercial operations: Q3 2026.

Pieter Krügel, CEO of Quantum Data Energy PLC, said: "We are delighted that construction and commissioning have been successfully completed at our Hindlip project, and ready for commercial operations. The project has been delivered in line with the latest timeline set out in our March announcement, below budget, and every item on the project risk register has been closed out. We would like to thank everyone involved in successfully delivering this project, especially the teams on site, Powertree as our funding partner, and NGED. Upon commencement of commercial operations, Hindlip will become our second operational flexible generation asset. The project represents a further step in implementing our strategy to build a portfolio of 300+ MW of flexible generation assets."

Stay up to date with QDE's latest news and updates by joining our email list and social media channels, as follows:

Website

https://quantumdata.energy

General enquiries

https://quantumdata.energy/contact

RNS email alerts

https://quantumdata.energy/news

LinkedIn

https://www.linkedin.com/company/quantum-data-energy-plc/

X (formerly Twitter)

https://x.com/QDEplc

YouTube channel

https://www.youtube.com/@quantumdata.energy

 

About Quantum Data Energy PLC:

Quantum Data Energy PLC (LSE: QDE) is a UK-based, revenue generating, independent energy company. The Company develops, operates, and owns energy production assets in the UK. The Company is listed on the London Stock Exchange Main Market. The Company delivers flexible, modular power solutions to the UK grid, and is pursuing a strategy to develop modular power solutions for AI datacentres, enabling scalable, reliable energy for next-generation digital infrastructure. The Company has deep expertise in infrastructure planning, grid access, gas access, and efficient power supply.

ENDS

This announcement contains inside information for the purposes of the UK version of the Market Abuse Regulation (EU No. 596/2014) as it forms part of United Kingdom domestic law by virtue of the European Union (Withdrawal) Act 2018 ('UK MAR'). Upon the publication of this announcement, this inside information is now considered to be in the public domain.

Pieter Krügel

contact@quantumdata.energy

Quantum Data Energy PLC

CEO

Guy Wheatley, CFA

+44 (0)203 4117773

Fortified Securities

Corporate Broker

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UK 100

Latest directors dealings