Review of Operations - Quarter ended 30 September

Summary by AI BETAClose X

Kore Potash plc reported its quarterly update for the period ended 30 September 2026, with a primary focus on clarifying the application of the Mining Convention in light of new mining laws in the Republic of Congo, which is crucial for progressing the Kola Project and the Formal Sale Process (FSP). The company currently holds approximately US$6.4 million in cash. The FSP is ongoing with two interested parties, following the withdrawal of one party and the addition of a new one. Front-End Engineering Design for the underground hoisting system is continuing due to a supplier change, and the Environmental and Social Impact Assessment is temporarily paused pending confirmation of design changes from strategic investors. Validation tests for the Kola Project's beneficiation process have been successfully completed, exceeding previous results for concentrate grade.