Hussar EP513 Mobilisation Update

Summary by AI BETAClose X

Georgina Energy PLC has provided an update on the mobilisation of the Ensign Rig 970 to the Hussar EP513 site, estimating an 8-10 week timeline from formal notification, subject to road closures and weather conditions. The company has completed all civil engineering and site works, but ongoing road issues and variable weather are causing delays and additional costs for rig reactivation and transport, which will be allocated between Ensign and Westmarket. Alternative routes are being reviewed by consultants. The Hussar prospect targets helium, hydrogen, and natural gas in subsalt reservoirs and fractured basement, with an independent report certifying unrisked prospective resources of 283 BCF helium, 315 BCF hydrogen, and 2.93 TCF hydrocarbon gas, equating to a potential in-situ value of approximately US$152 billion based on current pricing.