OPERATIONS UPDATE FOR THE SOUTH CROFTY TIN PROJECT

Summary by AI BETAClose X

Cornish Metals PLC has provided an operations update for its South Crofty tin project, reporting that underground and surface works are advancing, with the New Cook's Kitchen shaft mid-shaft pump station refurbishment completed and dewatering ongoing. The company is optimizing the project schedule by bringing forward pre-production development to Q3 2026, aiming for shaft refurbishment and dewatering completion in early 2027, while maintaining the mid-2028 guidance for first tin production. Process plant excavation and engineering are progressing, surface construction at Roskear shaft has commenced, and a surface exploration drilling program is planned for March 2026 to expand the mineral resource.