Company Update and Bond Update

Summary by AI BETAClose X

Ampeak reports its flagship Afon Wysg 1 (AW1) 240MWh BESS achieved financial close in August 2025 with £67.4m secured (including £45.3m non‑recourse), civil works and equipment delivered, energisation expected later this month and full commercial operations in Q1 2027; the company plans to double AW1 to 480MWh shortly after operation and its portfolio totals c.770MW/2.6GWh. Citing NESO connection timing risk, Ampeak proposes deferring debenture capital repayments of £2.0m, £3.0m and £7.7m by two years to 31/12/2028, 31/12/2029 and 30/6/2031, raising debenture interest to 13% p.a. from 1/1/2027 and deferring a 30/6/2027 interest payment, subject to 75% holder approval.