El Moto Mine Construction Update

Summary by AI BETAClose X

ABT raised gross IPO proceeds of approximately £142.5m (≈€170m) and reports El Moto construction progress with the main decline 60 metres developed, a 100,000 m³ water storage reservoir completed, a water treatment pilot plant operational, Phase 1 of a waste rock/tailings co‑disposal facility under way and 104 people on site; ABT entered a Conditional Credit Approved Term Sheet with Deutsche Bank for a Project Finance Facility, expects a Facility Agreement in Q1 2027 and Financial Close in Q2 2027, says IPO proceeds plus cash will fund construction through end‑2027, and continues to target first production in Q1 2029 under a 2026 DFS that envisages 1.5 Mtpa processing, >420,000 mtu WO₃/yr (≈370,000 mtu avg), 22.6 Mt reserves at 0.41% WO₃ and ~91 Mt resources at 0.38% WO₃.