Update on financing and mine development

Summary by AI BETAClose X

Pensana Plc has provided an update on financing and mine development for its Longonjo rare earth mine, with commissioning targeted for early 2028 and full production by late 2028. The company is seeking US$75-90 million in equity financing for its subsidiary Ozango Minerais sa, with major shareholder Cascade expected to deploy a significant tranche within 14 days, having already invested US$15 million of its US$165 million commitment. The Longonjo project, one of the world's largest undeveloped rare earth mines, is 30% complete in construction and over 60% committed in procurement, with a low phase 1 capex of US$250 million, an estimated EBITDA margin of 80%, and an NPV of US$2.3 billion. Initial production is planned at 20,000 tonnes per annum of mixed rare earth carbonate (MREC), expanding to 40,000 tpa in Year 4, with binding offtakes and debt approvals anticipated by February 2027.