Commissioning of Flotation Circuit and Completion of Phase 2 at Nalunaq

Summary by AI BETAClose X

Amaroq Ltd. has successfully completed Phase 2 at the Nalunaq gold mine with the commissioning of its flotation recovery circuit, which is now operational and performing at design specifications. This development is expected to significantly increase overall gold recovery from a gravity-only range of 50-70% to approximately 90-95%, materially enhancing gold production from the same ore feed. The company has produced its first gold concentrate, and previously processed gold-bearing tailings with approximately 6g/t will be reintroduced to the plant for additional recovery. Amaroq reiterates its FY2026 gold production guidance of 25-35 koz and confirms its H1 2026 production range of 7,000 to 10,000 oz of gold.