LukOil starts drilling at Filanovsky field

By BFN News | 01:28 PM | Thursday 07 December, 2017


LukOil has confirmed that the Company has finished most of the construction works at Vladimir Filanovsky field's Phase 2 development facilities and started drilling of the first production well. The drilling is planned to be completed in early 2018. The Phase 2 facilities will allow the Company to reach the stable designed production plateau of 6m tons per year at the field. There are six production and two injection wells operating at the Phase 1 facilities. The cumulative production from the field has surpassed 5m tons of oil. Story provided by StockMarketWire.com