West China Cement

Lantian Update

West China Cement Limited
23 January 2007


Lantian Update


The management are pleased to provide the following update on progress at
Lantian:


As stated in the Company's Admission Document at the time of admission to AIM in
December 2006, the second production centre is under construction at Lantian, 35
kilometres from Xi'an.  The directors are pleased with progress at Lantian where
commissioning of the milling capacity is expected to begin slightly ahead of
schedule in February. This will enable some early sales of cement produced from
bought in clinker. Firing of the kiln is expected to occur in March with the
plant scheduled to achieve design capacity from mid year.  Progress on the
Lantian 2 plant remains on schedule.