INTERIM STATEMENT FOR THE SIX MONTHS ENDED 30 JUNE 2016

 

Road Town, Tortola, British Virgin Islands (20 September 2016)

 

Chaarat (AIM - CGH), the AIM quoted exploration and development company with assets in the Kyrgyz Republic, today announces the intention to appoint a new non-executive Chairman, a refreshed strategic focus to achieve production and publishes its unaudited results for the period ended 30 June 2016.  

HIGHLIGHTS

·     Largest shareholder affirms his support for Chaarat by agreeing to join as non-executive Chairman

·     Development of Tulkubash Heap Leach Project (the "Tulkubash Project") confirmed

·     Tulkubash Project expected to process approximately 8,000 tonnes of ore per day to produce approximately 60-70,000 ounces of gold per annum 

·     GBM and WAI contracted and working on preparation of Bankable Feasibility Study for Tulkubash Project

·     Metallurgical and geotechnical drilling underway on site and due for completion by the end of the 2016 season

·     During the period to 30 June 2016 the results and initial optimisation of the NERIN Feasibility Study for the whole Chaarat Project were published

 

2016 has already seen significant developments in our progress towards the crystallisation of value from the Chaarat Project with the publication of the NERIN Feasibility Study.

Your Board has previously referred to the twin track strategy of seeking potential acquirers or joint venture partners whilst at the same time working on our own development plan for the Chaarat deposit.  The Board is now focussed on taking the Chaarat Project into production as it believes that this route will deliver greater value to shareholders.

The first stage on the road to production will be the Tulkubash Project.  An internal study based on the results of the recently completed NERIN Feasibility Study demonstrates this first stage will generate an acceptable return as well as minimising the initial capital outlay required to reach production. This will establish the foundations for the development of the second much larger project in due course.

Board update

Our largest shareholder Martin Andersson (who holds his shares through Labro Investments) is fully supportive of this strategy and we are delighted that he has agreed to lead the Board as non-executive Chairman.  Martin has significant experience of Russia and the region. He is a private investor with a wide range of interests, predominantly in real estate and technology.

Martin will be joined on the Board by his associate Martin Wiwen-Nilsson, who will also be a non-executive director. Martin spent 21 years at Goldman Sachs, where he was a Partner from 2008 to 2015. During his time there he held leadership positions in, amongst others, the emerging markets, commodities and sovereign wealth fund businesses.

Both new directors will provide guidance, knowledge and introductions to contacts from their extensive networks to inform Chaarat's strategy. Both the appointment of Martin Andersson as non-executive Chairman and Martin Wiwen-Nilsson as non-executive director are subject to Board approval which is anticipated shortly.

On the appointment of Martin Andersson to the Board, Christopher Palmer-Tomkinson will step down as Chairman.  The Board is very grateful for his wisdom and guidance since Chaarat's admission to AIM in 2007.

Background to staged development approach

Our decision to pursue a staged development for the large Chaarat deposit was determined by two factors. The first is the type of ore contained in the deposit and the available processing options for gold extraction. The second is the proposed future developments to processing infrastructure in the Kyrgyz Republic which will have a positive effect on the economics of the Chaarat Project.

1.    Ore and processing options
Large gold deposits in the belt from Turkey in the west, via Russia and through China in the east, also contain the combination of free milling and refractory ores found at Chaarat where both types of ore are contained within Chaarat's three Zones (Tulkubash, Contact and Main).  
 

The Tulkubash Zone contains "free milling" ore from which gold can be recovered by conventional cyanide leaching.  The Contact and Main Zones contain refractory sulfide ore which requires a more capital intensive process to extract the gold, either by producing concentrate, which then needs to be smelted, or by oxidising the ore before leaching.

 

2.    In country development

The Kyrgyz Government is seeking to retain the added value from processing refractory ore in country which is lost if concentrate is transported abroad for smelting. It has therefore recently signed a binding agreement with a Turkish company to build a smelter near the Chaarat deposit.  Once the smelter is built Chaarat will have the option to produce concentrate from its refractory ore and have it processed locally.   This processing option means that the construction of our own oxidation unit can be postponed.

Whilst awaiting developments in the processing options for refractory ore, Chaarat will be able to achieve production from the Tulkubash Project.

  

Previous small scale production plan

 

Shareholders will recall our plan in 2011 to move to small scale production by building a standard Carbon in Leach ("CIL") plant to process the free milling ore from the Tulkubash deposit. We originally estimated there was enough ore for three years of processing (to achieve production of 20-30,000 ounces of gold per year) and the capital costs involved included a mill, a power line and tailings dam.

 

Once in production we intended to add either a flotation unit (to generate and sell concentrate) or increase the size of the plant and add an oxidation unit to oxidize the refractory ore which would then be treated by the same CIL unit. The general design of the plant and the more detailed engineering and tender for construction of the first phase were completed. 

Further metallurgical testing of the ore from the Tulkubash deposit then established that it is amenable to heap leaching. This is a relatively low cost processing method (both in terms of capital and operating costs) and uses a well-established and uncomplicated technology. Extracting gold via a heap leach reduces the capital requirements as a mill and tailings dam are not required. Generators can initially provide sufficient power and a power line can be constructed at a later date.

By 2013 we were aware that uncertainty in the market conditions could have made our production plans uneconomic. We therefore put production on hold pending completion of the NERIN Feasibility Study for the whole Chaarat Project. This decision proved to be wise, as evidenced by the demise of a number of our peers who, whilst reaching production, were unable to develop sustainable businesses. 

Why a Chinese Feasibility Study?

In February 2016 we announced the results of the Feasibility Study prepared by NERIN for the Chaarat Project and in April the results of the initial optimisation. One rationale for seeking a Chinese prepared Feasibility Study was to set a benchmark valuation for negotiations with potential Chinese acquirers.  This benchmark was duly set at in excess of 20 times the market capitalisation of Chaarat shares at that time. The Chaarat share price has continued to trade at a substantial discount to the value of the ounces of gold in the ground as set out in the NERIN Feasibility Study. The Board has therefore concluded that it is not possible to sell the Company at this developmental stage for a sensible price.

Interest in the Chaarat Project from Chinese companies is still in evidence but there is, more generally, a noticeable bias towards acquisitions of assets which are already in production and therefore substantially derisked. 

What next for the Tulkubash Project?

We took the opportunity of the suspension of our previous production strategy to invest funds in infrastructure and further exploration to increase the size of the Tulkubash resource.  Based on this work we announced a revised JORC resource of just over 7 million ounces in June 2016 (an increase of 15%). The Tulkubash Zone resource itself was increased by 26% to 912,000 ounces and therefore comprises 13% of the total resource.

Our plan now envisages a processing capacity of 2.8 million tonnes of ore per year which (based on the recovery achieved in previous metallurgical testing) would result in production of 60-70,000 ounces of gold per year with a mine life slightly in excess of five years. This triples the production capacity from the Tulkubash Project as originally estimated in 2011 from a three year life of mine.

We believe that the Tulkubash resource can be increased by further drilling as we have identified that it continues along strike and at depth.  Our internal studies, prepared on the basis of the NERIN Feasibility Study work, show that the returns generated within five years from the Tulkubash Project will comfortably exceed the estimated capital investment required for its development.

A Feasibility Study for the Tulkubash Project

In order to optimise the results of the work undertaken by NERIN on the Tulkubash Project within their Feasibility Study and to ensure the level of reliance on those results is at a "bankable" level, we have commissioned GBM and Wardell Armstrong International ("WAI") to prepare a Bankable Feasibility Study for the standalone stage one Tulkubash Project. 

This Bankable Feasibility Study will provide the basis for us to raise funds for construction and production, establish the most efficient layout for the Tulkubash Project, provide confirmation on the metallurgy and recoveries from the free milling ore and assist with the tendering for equipment.

One of the key determinants of the economics of the Tulkubash Project is the recovery of gold achieved from the heap leach process. We are therefore planning to verify previous test results by reperforming the work on new ore samples. Consequently drilling is now underway on site to extract large samples for metallurgical testing.  We are also undertaking further geotechnical drilling to confirm the suitability of the proposed layout of the Project.

We are well placed to capitalise on our work over the last three years. 

·   We have completed additional drilling within the Tulkubash Zone to increase the resource and therefore prospective gold production;

·   We have achieved the social licence to operate a heap leach project - the first in the country; 

·   We have a mining licence until 2032;

·   All payments to the Government in respect of the delineated resource to obtain the mining licence have been made;

·   A significant portion of the Project infrastructure is in place - roads, bridge, camps, a workshop and a fuel tank farm; 

·   The access road has been designed;

·   The land needed to cover the whole footprint of the Project has been identified and the formal allocation is in progress; and

·   The site has been "sterilised" of alluvial gold deposits in preparation for construction of the mine.

The provisional timetable to production is now:

·   Completion of the Bankable Feasibility Study for the Tulkubash Heap Leach Project in the first half of 2017;

·   Completion of the local approvals process for the Project - aiming for the third quarter of 2017;

·   Work on the financing to continue during 2017 with the aim of raising finance for construction in the third quarter of 2017; and

·   Subject to completion of the local approvals process and financing, construction is to begin in the first quarter of 2018, provisionally targeting the first gold pour in 2019.

What about the second stage?

We have by no means overlooked the fact that the Contact and Main Zones contain 87% of the ore at Chaarat.  Currently only two main options exist to develop this section of the deposit.  The first is to process the refractory ore in order to produce concentrate which requires a smelter to produce gold from the concentrate.  We have looked at the option of sending concentrate to China for processing and this approach would be uneconomic.   The construction of a smelter near Chaarat would accelerate the possibility of building a second stage project based on the refractory ore in the Main and Contact Zones by generating a smeltable concentrate. 

The second processing option is to build an oxidation unit for the pre-treatment of the ore prior to cyanidation.  The type of oxidation unit needed to achieve the highest recoveries from the Chaarat refractory ore would require a very high capital cost based on current technologies. 

Hence the first option, to produce concentrate, would be preferable since it is a less technically complex and has a much lower capital cost.    

Given the technical developments which are being made to achieve more efficient processing of refractory ore, we consider that the economics of the second stage development of the Chaarat Project could become significantly more attractive in the short term.  In the meantime we have the prospect of extending the production life of the Tulkubash Project.

Funding and corporate update

During the period under review we realised USD 1.2 million from the sale of fixed assets and reduced headcount to a permanent staff of 27, supplemented by approximately 70 temporary staff during the season, most of whom are based on site.  As at 30 June 2016, the Company had cash and cash equivalents of USD 2.06 million.

We will be working with our largest shareholder to review our options for additional funding in the light of our renewed production strategy.

The Board is also taking the opportunity of the renewed focus on production to align the interests of the management with shareholders by cancelling all existing share options held by directors and certain key members of staff in Bishkek, which are significantly out of the money. New options will be issued at a price to be determined by the Board in due course.

 Dekel Golan CEO commented: "I am delighted to welcome our new Chairman and director to the Board at this pivotal time in the Chaarat story and look forward to working with them.   The whole Board is hugely appreciative of the patience and support shown by our loyal shareholders. I know it may have seemed to them that nothing was happening at the Chaarat Project but, as we have now demonstrated, we have implemented concrete plans to achieve production in the near future.

I am also very grateful for the wise counsel of Christopher, our outgoing Chairman, which I am sure, will still be available to me and the rest of the Board."  

Dekel Golan
Chief Executive Officer

 

Enquiries:  

Chaarat Gold Holdings Limited

+ 44 20 7499 2612 

c/o Central Asia Services Limited  

info@chaarat.com

Dekel Golan   CEO                  

Linda Naylor  FD

 

 

Numis Securities Limited

+44 (0) 20 7260 1000

John Prior, Paul Gillam (NOMAD)
James Black (Broker)

 

 

 About Chaarat Gold

Chaarat Gold is an exploration and development company operating in the Kyrgyz Republic with a large, high grade resource - the Chaarat Gold Project. The Company's key objective is to become a low cost gold producer generating significant production from the development of the Chaarat Gold Project. Chaarat is engaged in an active community engagement programme to optimise the value of the Chaarat investment proposition. 

Chaarat aims to create value for its shareholders, employees and communities from its high quality gold and mineral deposits in the Kyrgyz Republic by building relationships based on trust and operating to the best environmental, social and employment standards.

 

Further information is available at www.chaarat.com

 

 

 

 

Consolidated income statement

 

 

 

 

 

For the six months ended 30 June

 

 

 

 

 

 

 

6 months to

30 June

2016

(unaudited) 

6 months to

30 June

2015

(unaudited) 

12 months to
31 December
 2015
(audited)

 

 

 

USD

USD

USD

 

Exploration expenses

 

(991,276)

(787,523)

(2,115,164)

 

 

Administrative expenses

 

(1,568,432)

(1,379,582)

(2,551,262)

 

- Share options expense

 

(981)

(45,436)

(90,869)

 

- Foreign exchange gain/(loss)

 

3,808

(24,798)

20,187

 

Total administrative expenses

 

(1,565,605)

(1,449,816)

(2,621,944)

 

Other operating income/(expense)

 

589,327

65,449

-

 

Operating loss

 

(1,967,554)

(2,171,890)

(4,737, 108)

 

Finance income

Taxation

 

17,312
-

26,529

     -

132,752

    -

 

 

Loss for the period, attributable to equity shareholders of the parent

 

(1,950,242)

(2,145,361)

(4,604,356)

 

 

Loss per share (basic and diluted) - USD cents

 

(0.71)

(0.79)

(1.69)

 

 

 

 

 

 

 

                 

 

 

 

Consolidated statement of comprehensive income

 

 

 

 

 

For the six months ended 30 June

 

 

 

 

 

 

 

6 months to

30 June

2016

(unaudited) 

6 months to

30 June

2015

(unaudited) 

12 months to
31 December
 2015
(audited)

 

 

 

USD

USD

USD

 

 

Loss for the period, attributable to equity shareholders of the parent

 

(1,950,242)

(2,145,361)

 

(4,604,356)

 

 

 

 

 

 

 

Other comprehensive income:
Items which may subsequently be reclassified to profit and loss

 

 

 

 

 

Exchange differences on translating foreign operations and investments

 

2,689,088

(1,311,157)


(7,708,129)

 

Other comprehensive income for the period, net of tax

 

2,689,088

(1,311,157)

 

(7,708,129)

 

 

 

 

 

 

 

Total comprehensive loss for the period attributable to equity shareholders of the parent

 

738,846

(3,456,518)

(12,312,485)

 

 

 

 

 

 

 

                 

 

 

 

 

Consolidated balance sheet

 

 

 

 

 

 

At 30 June

 

 

 

 

 

 

 

 

 30 June

2016

(unaudited) 

 30 June

2015

(unaudited) 

 

31 December
 2015
(audited)

 

 

 

USD

USD

 

USD

 

Assets

 

 

 

 

 

 

Non-current assets

 

 

 

 

 

 

Intangible assets

 

31,042

41,399

 

29,505

 

Mine properties

 

21,764,870

22,268,925

 

19,797,277

 

Property, plant and equipment

 

906,746

3,129,417

 

2,174,678

 

Assets in construction

 

10,185,681

11,964,950

 

9,259,089

 

 

 

32,888,339

37,404,691

 

31,260,549

 

Current assets

 

 

 

 

 

 

Inventories

 

360,134

763,523

 

306,111

 

Trade and other receivables

 

254,165

728,884

 

212,845

 

Cash and cash equivalents

 

2,063,517

5,156,510

 

2,839,159

 

 

 

2,677,816

6,648,917

 

3,358,115

 

Total assets

 

35,566,155

44,053,608

 

34,618,664

 

 

 

 

 

 

 

 

 

Equity and liabilities

 

 

 

 

 

 

 

 

 

 

 

 

 

Equity attributable to shareholders

 

 

 

 

 

 

Share capital

 

2,729,353

2,729,353

 

2,729,353

 

Share premium

 

132,108,746

132,108,746

 

132,108,746

 

Share warrant reserve

 

1,358,351

1,358,351

 

1,358,351

 

Other reserves

 

14,926,889

15,038,993

 

14,952,340

 

Translation reserve

 

(15,839,768)

(12,131,884)

 

(18,528,856)

 

Accumulated  losses

 

(100,328,935)

(96,078,216)

 

(98,405,125)

 

 

 

34,954,636

43,025,343

 

34,214,809

 

 

 

 

 

 

 

 

Current liabilities

 

 

 

 

 

 

Trade payables

 

132,663

386,181

 

176,641

 

Accrued liabilities

 

478,856

642,084

 

227,214

 

 

 

611,519

1,028,265

 

403,855

 

Total liabilities

 

611,519

1,028,265

 

403,855

 

Total liabilities and equity

 

35,566,155

44,053,608

 

34,618,664

 

 

 

 

 

 

 

               

 

 

 

 

 

 

 

 

Consolidated statement of changes in equity

 

For the six months ended 30 June

 

 

Share capital
USD

Share premium USD

Share warrant reserve
USD

Accumulated losses
USD

Translation reserve
USD

 

Total
USD

 

 

 

 

 

 

 

 

 

Balance at 31 December 2014

2,729,353

132,108,746

 

1,358,351

 

(94,144,808)

15,205,510

(10,820,727)

46,436,425

 

Currency translation

-

-

-

-

-

(1,311,157)

(1,311,157)

 

Other comprehensive income

-

-

-

-

-

(1,311,157)

(1,311,157)

 

Loss for the six months ended
30 June 2014

-

-

-

(2,145,361)

-

-

(2,145,361)

 

Total comprehensive income  for the six months ended
30 June 2014

-

-

-

(2,145,361)

-

(1,311,157)

(3,456,518)

 

Share options lapsed

-

-

-

211,953

(211,953)

-

-

 

Share options expense

-

-

-

-

45,436

-

45,436

 

Balance at 30 June 2015

2,729,353

132,108,746

 

1,358,351

 

(96,078,216)

15,038,993

(12,131,884)

43,025,343

 

Currency translation

 

 

 

 

 

(6,396,972)

(6,396,972)

 

Other comprehensive income

 

 

 

 

 

(6,396,972)

(6,396,972)

 

Loss for the six months ended
31 December 2015

 

 

 

(2,458,995)

 

 

(2,458,995)

 

Total comprehensive income for the six months ended
31 December 2015

 

 

 

( 2,458,995)

 

(6,396,972)

(8,855,967)

 

Share options lapsed

 

 

 

132,086

(132,086)

 

 

 

Share options expense

 

 

 

 

45,433

 

45,433

 

Warrant expense

 

 

 

 

 

 

 

 

Issuance of shares for cash

 

 

 

 

 

 

 

 

Share issue cost

 

 

 

 

 

 

 

 

Balance at 31 December 2015

2,729,353

132,108,746

1,358,351

(98,405,125)

14,952,340

(18,528,856)

34,214,809

 

Currency translation

 

 

 

 

 

2,689,088

2,689,088

 

Other comprehensive income

 

 

 

 

 

2,689,088

2,689,088

 

Loss for the six months ended
30 June 2016

 

 

 

(1,950,242)

 

 

(1,950,242)

 

Total comprehensive income  for the six months ended
30 June 2016

 

 

 

(1,950,242)

 

2,689,088

738,846

 

Share options lapsed

 

 

 

26,432

(26,432)

 

 

 

Share options expense

 

 

 

 

981

 

981

 

Balance at 30 June 2016

2,729,353

132,108,746

1,358,351

(100,328,935)

14,926,889

(15,839,768)

34,954,636

 

                     

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Consolidated cash flow statement

 

 

 

 

 

For the 6 months ended 30 June

 

 

 

 

 

 

 

6 months to

30 June

2016

(unaudited)

6 months to

30 June

2015

(unaudited)

12 months to
31 December
 2015
(audited)

 

 

 

USD

USD

USD

 

Operating activities

 

 

 

 

 

Loss for the period

 

(1,950,242)

(2,145,361)

(4,604,356)

 

Adjustments:

 

 

 

 

 

Amortisation expense - intangible assets

 

3,580

6,953

11,400

 

Depreciation expense - property, plant and equipment

 

197,905

293,314

578,096

 

(Profit)/loss on disposal of property, plant and equipment

 

(154,700)

45,227

(86,580)

 

Provision for inventories

 

-

-

268,692

 

Finance income

 

(17,312)

(51,327)

(132,752)

 

Share based payments

 

981

45,436

90,869

 

Decrease in inventories

 

(15,557)

84,295

147,538

 

(Increase)/Decrease in accounts receivable

 

(1,688)

(2,498)

153,680

 

Increase/(Decrease)in accounts payable

 

291,999

(384,173)

(322,778)

 

Net cash flow used in operations

 

(1,645,034)

(2,108,134)

(3,896,191)

 

Investing activities

 

 

 

 

 

Purchase of tangible fixed assets

 

(28,351)

(8,836)

(220,711)

 

Capitalisation of development activities

 

(181,138)

(487,568)

(1,213,724)

 

Proceeds from sale of equipment

 

1,224,585

326,601

449,801

 

Interest received

 

17,312

26,529

132,752

 

Net cash used in investing activities

 

1,032,408

(143,274)

(851,882)

 

Financing activities

 

 

 

 

 

Proceeds from issue of share capital

 

-

-

-

 

Issue costs

 

-

-

-

 

Net change from financing activities

 

-

-

-

 

Net change in cash and cash equivalents

 

(612,626)

(2,251,408)

(4,748,073)

 

Cash and cash equivalents at beginning of the period

 

2,839,159

7,608,865

7,608,865

 

Effect of changes in foreign exchange rates

 

(163,016)

(200,947)

(21,633)

 

Cash and cash equivalents at end of the period

 

2,063,517

5,156,510

2,839,159

 

                         

 

 

 

 

Notes to the financial statements

 

1       Loss per share

The loss per share is calculated by reference to the loss of USD 1,950,242 for the six months ended 30 June 2016 and the weighted average number of shares in issue of 272,935,389 during the period. There is no dilutive effect of share options.

 

2       Basis of preparation of financial statements

The financial information set out in this interim statement does not constitute statutory accounts.

The unaudited results for the period ended 30 June 2016 have been prepared on the basis of the accounting policies adopted in the audited accounts for the year ended 31 December 2015. The results for the period are derived from continuing activities. The figures for the period ended 31 December 2015 have been extracted from the statutory financial statements, prepared under IFRS, which are available on the Group's website www.chaarat.com. The auditor's report on those financial statements was unqualified.

 

The Group had cash and cash equivalents of USD 2.06 million and no borrowings at 30 June 2016. The Board is in the process of identifying sources of additional funding and has a reasonable expectation that additional funds will be made available from existing and new shareholders. Other sources of funds include  selling equipment and other assets of the Group, cutting discretionary expenditure, reducing headcount, reviewing the timing of other expenditure and pursuing other fund raising options.      

Subject to the successful realisation of these expectations, the Board is satisfied that it has sufficient funds to maintain the Group as a going concern and therefore considers it appropriate to prepare these unaudited results on a going concern basis.

However, in the absence of such arrangements being in place, these conditions indicate the existence of a material uncertainty which may cast significant doubt over the Group's ability to continue as a going concern and, therefore, that it may be unable to realise its assets and discharge its liabilities in the normal course of business. The financial statements do not include the adjustments that would result if the Group was unable to continue as a going concern.

 

 

 


This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
IR GGURGBUPQGBB
UK 100

Latest directors dealings